|
Building for the Future
Carpenter's Union Gets New Arizona Headquarters
By K. Robert Wendel
The new Southwest Regional Council of Carpenters Arizona
headquarters would make even Tim the tool man envious.
Imagine nearly 60,000 sq. ft. of shop space with table and
radial saws, shapers, borers, lathes, joiners and a host of
other wood working equipment. The project will also feature
a large dust collection system, a welding shop, an exposed
earth area where carpenters can practice concrete formwork
and high ceilings for scaffold training.
The new carpenters headquarters will train carpenters, millwrights,
cabinetmakers and dry wall installers for careers in the construction
industry.
|
"This is going to be our flag ship," said Southwest
Regional Council of Carpenters Arizona executive director
for training Tom Quine. "We have the latest and greatest
technology throughout the building and all of the classes
are also wired."
The project is really two buildings in one. A two-hour firewall
separates the shop area from approximately 70,000 sq. ft.
in two stories, with offices, classrooms, an administration
area and a 499-seat meeting hall. Contractors used tilt-up
concrete panels sitting on a slab-on-grade foundation for
the building, with a three-ply built-up roof.
The front section facing McDowell Road is where architects
concentrated their design efforts, with a grand driveway and
lobby that will feature the carpenter's council logo in a
terrazzo floor. Architects used curtain wall systems to break
the building's massing.
In the rear part of the building, designers incorporated high
windows for natural lighting as well as wood glue-lam beams
as a tie-in to the carpenter's trades. While the front building
utilizes rooftop heat pumps allowing each work space its own
thermostat, the shop area uses swamp coolers.
Work on the 139,000-sq.-ft project on 43rd Avenue and McDowell
began in spring, with general contractor Kitchell Contractors
starting site work on the graded industrial lot.
Morrison Majerle Inc. of Phoenix performed the civil engineering
work while Speedie & Associates did soil analysis and
materials testing. Although the carpenter's council wanted
to construct the building with wood framing, the size and
variety of functions precluded the option.
"The carpenters really wanted to do the entire structure
in wood, but the size of the building as well as the uses
were such that the building code really wouldn't permit it,"
said Michael Violette, an architect with project designer
Leo A Daly in Phoenix. "We would have used a lot more
wood at that site, but the codes really restricted the amount
of wood, mainly because of the large conference hall."
While the use of wood was limited, architects attempted to
incorporate the material wherever possible. The project features
extensive woodwork as well as a monumental staircase utilizing
glue lam beams as treads and risers. Since the project is
really a showcase for the carpenter's council, a lot of attention
is being paid to the craftsmanship.
"The wood work really has to be straight, true and plumbed,
which became a challenge in a good way," said Leo A Daly
project designer Greg Woods . "We have a lot of guys
looking at this with a very critical eye, so each subcontractor
working on this project has to watch their own work to make
sure they are providing the quality craftsmanship."
|