|
Take Me Out to the Ball Park
By K. Robert Wendel
In an age of mega stadiums, the Phoenix Municipal Baseball
Park stands out as an intimate ballpark that recreates the
excitement and familiarity of baseball, before the megastars
and huge salaries.
The stadium is also known for its unique accordion roof structure.
So when the city of Phoenix decided to remodel the park, which
was constructed in 1962, much of the discussion revolved around
the park's signature roof. Although initial programming called
for its removal, the building team renovating the stadium
was convinced the roof could be saved and integrated into
the renovated park.
"The programming study by the prior firm essentially
removed the roof," said Jason Boyer, a senior associate
with project architect Gould Evans & Associates of Phoenix.
"We felt the roof's character is essential to the stadium.
It's one of the more iconic elements of architecture in Phoenix
and we wanted to save that."
|
General contractor Barton Malow Co. of Phoenix was then
faced with the all-too-common task of putting 10 lbs. of stuff
into a 5-lb. bag. The $8 million renovation called for a complete
upgrade on the press box; more office space for the Oakland
A's, who use the field as home during spring training; and
a complete rework of the park's landscaping and hardscaping.
"It's going to be an all new ball park," said Barton
Malow, project manager Tom Harrison. "We have done a
lot of things to improve the fan and player experience and
people are really going to notice the difference."
To preserve the roof, other means were needed to supply the
renovated press box with electrical and mechanical upgrades
to meet the media demands.
Contractors removed much of the mortared rock wall to create
a new mechanical and electrical space underneath the existing
press box. Engineers then designed a mechanical system utilizing
a plenum, along with variable air volume boxes and a split-system
air handler.
Associated Engineering Inc. of Phoenix extensively upgraded
the electrical and data capabilities to handle the demands
of the high-tech media.
"It was tight underneath the press box, so we put in
a plenum underneath the press box, rather than ducting the
return air back," said Peter Kunka of Phoenix-based Kunka
Engineering Inc. "The project has so many seemingly minor
things involved, but the whole thing comes together to give
a better experience at the ball park."
Crews from Ace Asphalt of Phoenix faced a tight site when
excavating for a new elevator shaft near the press box. With
no room for shoring and a host of sewer and optical lines,
workers had to lay back >> the slope to a one-to-one
ratio, especially after running into structural concrete 18
ft. below grade.
"It was a touchy situation but we got through it okay,"
said Ace Asphalt senior project manager Jim Troncale. "We
used the existing building structure as one shore wall, but
we had to lay the two sides back at one to one. There wasn't
a whole lot of room."
A second floor was added to the Oakland A's office, which
essentially doubled the team's floor space and provides a
better view of the field.
The original office featured existing precast concrete double
Ts, so engineers believed the building could take the weight
of another story. But in the end, steel columns were installed
to the basement to support the extra floor.
A metal pan deck with a 2.5-in. concrete topping provided
the floor for the next level, with the walls constructed of
load-bearing masonry. Centimark Roofing of Phoenix capped
off the new office, as well as re-roofing the accordion roof.
"Originally, the roof was an amalgamation of paint and
goo and everything in the world," said Centimark Roofing
senior project manager Rick Fennemore. "It had been leaking
for some time. The roof conditions were really conducive to
spray foam, given the uneven surface and the odd angles. It
would have been too much work trying to make the relief cuts
if we would have used sheet roofing."
As part of the overall project, Barton Malow also constructed
a new maintenance shed, and the field's lighting was upgraded
and improved. Crews added two new entrances, along with aboutsome
4,000-cu. yds. of new hardscape featuring decorative and colored
concrete.
"There's a lot of really decorative concrete," said
Dan Gonzales of RBG Concrete of Phoenix said. "The hardscape
was difficult because his firm had to make sure the banding
came out, but it was an exciting experience."
|