|
Bouncing Back
It started out as a controlled Forest Service burn in May
2000, but by the time it was extinguished two months later,
the Cerro Grande Fire in Los Alamos, N.M., destroyed more
than 48,000 acres of pristine forest.
Nearly 250 structures were also lost, and 11,000 residents
were forced to flee as the fire consumed their homes and businesses.
Now, the small mountain community is tackling the rebuilding
process in earnest with funds from the federal and state governments
to rebuild 8.5- mi. of residential streets and thousands of
feet of new utilities.
Albuquerque's AUI Inc. recently embarked on a two-year, $24
million project to get the area back on its feet. AUI Inc.
won two phases of the project, which started in September.
|
Twin Mountain Construction of Albuquerque is also working
on a phase, concentrating on drainage issues in the area.
Project engineers included the Albuquerque offices of URS
Corp. and CDM.
"The damage to the streets came from the heavy equipment
fighting the fires and then with the amount of construction
rebuilding homes, it all compounds the wear and tear,"
said AUI lead project manager Sam Garrell. "After the
fire, we had rain and it jammed up the culverts with silt
and they flooded over and washed out parts of the road. There's
just a lot of work to be done."
Contractors have a lot of digging on the project, which calls
for 38,000 lin. ft. of new electrical duct banking, 45,000
lin. ft. of new water line, 16,000 lin. ft. of new gutter
and the removal and replacement of 145,000 sq. yds of asphalt.
Most of the new waterline is 8-in. ductile pipe, but some
sections contain 48-in. high density polyethane.
The work is taking place in a congested area, with contractors
competing for space with local residential construction crews
and with traffic on the small, narrow roads.
Keeping traffic moving through the construction site is one
of the biggest headaches facing crews.
"Access is the key to this job," said AUI utility
project manager Gary Huffman. "It's a constant battle
trying to do our work while keeping access open, but the residents
have been good to work with. They understand you have to give
a little to get a little."
Crews are employing milling machines to take up much of the
asphalt and will reuse the tailings as a base course for the
new asphalt roads. Many of the roads have steep, 12 percent
grades, and on top of cold weather, paving the new roads has
been a juggling act.
Crews are concentrating on the utility work in the winter
and plan to begin paving this summer.
"It's the beginning of closure," Garrell said. "We
are seeing more and more homes being rebuilt and a lot of
old homes are being replaced. It's going to take time, but
it's going to happen.
|