|
Digging It
Railway Trench to Improve Traffic in Downtown Reno
By Tony Illia
A depressed rail trench similar to the Alameda Corridor is
under construction in downtown Reno. The $264.8 million, 2.25-mile-long
project, called ReTRAC (Reno Transportation Rail Access Corridor),
is expected to greatly relieve traffic congestion.
The 50-month undertaking will create a 33-ft.-deep, 54-ft.-wide
rail trench between West Second and Sutro streets, with 11
at-grade bridge crossings. Granite Construction Co. Inc.,
Watsonville, Calif, is the design-build general contractor
with Parsons Transportation Group, Pasadena, Calif., as its
engineer. Construction costs are $171 million. Pasadena, Calif.-based
Jacobs Engineering Group Inc. is reTRAC's project manager,
a contract worth $8.8 million. After design and right-of-way,
major construction began on January 4, 2004.
|
"This is going help tremendously in keeping traffic
moving through the downtown area," says Daviera Powell,
city spokesperson. "[Union Pacific] is talking about
having 24 trains a day run through downtown by next year up
to 36 trains daily by 2030."
The project is a critical component to the Port of Oakland's
$1.2-billion expansion and upgrade. Although only 10 percent
of Oakland's port cargo, or 98,900 containers, now travel
by train that number is expected to grow by 30 percent or
574,590 more containers by 2010. Reno's train traffic, which
runs through downtown, will consequently double by 2005. Union
Pacific agreed to turn over their 54-ft.-wide easement rights
and contribute $60 million to the project.
The remaining amount will be paid through a $115 million bond
sale, issued by New York-based Goldman, Sachs & Co., with
the debt being retired over 40 years through a combination
of a sales, room and property taxes. Other contributing funds
include a $50.5 million Federal Highway Administration loan,
plus Nevada Dept. of Transportation funds.
Originally approved in 1938, the project was to have been
started in January 1942, but was interrupted by World War
II. Later, the trench was shelved due to funding costs. As
the city's largest and most complex project, ReTRAC will require
661,000-cu. yds.
worth of excavation and 250,000-sq. ft. of soil nail wall
shoring to complete.
A temporary or "shoo-fly" track will be built to
reroute train traffic as excavation beings.
By using a combination of conventional layback, temporary
shoring and tieback methods, Granite will excavate to just
above the water table before installing a waterproof cutoff
wall that will require approximately 3,000 2-ft.-dia. drilled
piles. After 150,000-cu. yds. of wet excavation, Granite will
then place 38,000-cu. yds. of tremied concrete inside the
trench to create a waterproof seal across the bottom. One
million gallons of water will then be pumped-out, after which
141,000-cu. yds. of concrete will be placed. It will form
a U-shaped, 3-ft. thick concrete channel that serves as the
permanent trench structure. The feat will require 14,100-truck
loads worth of concrete and 100,000 cu. yds. of backfill to
complete.
"The thickness of the channel was needed since the trench
is below the water table," says Al Lord, Granite's trench
superintendent.
Two mainline rail tracks will run inside the trench corridor,
achieving speeds of up to 60-m.p.h. Meanwhile, vehicle traffic
will pass overheard on 11 concrete pre-cast bridge structures
measuring 4-ft.-wide by 54-ft.-long.
Nolte Associates Inc., Walnut Creek, Calif., who performed
the $6.2 million environmental impact statement and preliminary
engineering, has been hired by Parsons to design the bridge
and trench structures.
City officials placed stringent traffic restrictions upon
Granite when working in downtown Reno. For example, no two
adjacent streets can be closed in the project area. In addition,
one-lane of traffic must remain open on Third Street, and
two-lanes must always stay accessible on Plaza Street.
Although Granite has a lump sum fixed-price contract, it still
faces five milestone completion dates with liquidated damages
of up to $10,000-a-day. An estimated 250 workers will be onsite
during the height of construction activity. The ReTRAC is
expected to become operational by late 2005 with final project
completion by September 2006.
|