|
A Fab Project
by K. Robert Wendel
The next step in the silicon revolution is under way at Sandia
National Labs in Albuquerque, where contractors are erecting
three new buildings to provide cutting edge technology for
the U.S. government.
General contractor M.A. Mortenson of Texas started work in
June on the first building in the Microsystems Engineering
Sciences Application program, or MESA. The 98,000-sq.-ft.,
$80 million total cost project will provide clean rooms to
replace those in an older fab at Sandia. It will tie into
the existing fab, which will see some renovations.
The second project, a 131,000-sq.-ft. micro-lab, started in
November, with Texas-based Hensel Phelps Construction >>
moving earth on the $66 million total cost project. The third
building, a weapons integration facility, is expected for
bidding in July. The 162,000-sq.-ft. project is expected to
cost $89 million in total.
|
The project is the largest capital program ever undertaken
at Sandia, with plans for a 2007 program completion.
"This is one of the largest investments in the free world
in the micro-technology area," said William Jenkins,
Sandia National Lab project manager. "This is also a
major investment for national defense."
The Sandia National Labs are responsible for the design and
maintenance of 90 percent of the several thousand parts in
any given weapons system.
All three projects are being constructed in a sustainable
manner under Leadership in Engineering and Environmental Design
guidelines. The owners hope to achieve a "silver"
rating.
The micro-fab project is essentially a small, research and
development production line to create silicon and compound
semi conductors. One of the applications for the chips made
in the lab is to detect when chemical agents are deployed.
Because of the extremely tight tolerances required in chip
production, vibration control was a key issue. The $80 million
fab project sits on a 40-in. matt slab with the grade floor
on 36-in. waffle slab surrounded by a steel frame. More than
10,000 cu. yds of concrete with a fly-ash mix will be used.
Another 2,100 tons of steel is used in the frame.
Designers are relying heavily on concrete to create the vibration-free
buildings, with steel frames used in places where vibration
control was not an issue. Like other fabrication plants, the
project employs a large clear-span space at 102 ft., with
a fan deck above the fab that provides the mechanical requirements.
"All three buildings had strict vibration criteria,"
said Lisa Webster, a project manager with Albuquerque's Chaves
Grieves Consulting Engineers. "In the parts that don't
have the vibration requirements, we used steel, which is more
economical."
Designers faced several problems when drawing up the plans.
One was designing a building for high-tech production tools
that don't even exist yet. Designers needed to maintain flexibility
for future technologies that are yet to be developed.
"One of the biggest challenges was providing a balanced
response to the plethora of technical requirements that are
out there," said Paul Maute, a project manager for the
Texas office of Carter Burgess, the architect and mechanical,
electrical and plumbing engineer on all three buildings.
"Providing the final infrastructure with the flexibility
to accommodate changes in the market and the technology has
been difficult. You have to have some real conceptual engineers
to design for equipment that doesn't exist yet."
Dallas-based M.W. Zander designed the ISO Class 4 (class 10)
16,000-sq.-ft. clean room in the micro fab building.
Working next to the old microchip fabrication plant was another
challenge facing contractors. When moving earth or compacting
soil, crews often had to work around the schedule of the nearby
operating fab.
"Working next to an operating fab always presents problems,"
said Kelly Davis, a senior project manager for M.A. Mortenson.
"There were a lot of restrictions against vibration,
so that complicated our compaction efforts."
In addition to the three buildings, contractors are also constructing
two CUBs, or central utility buildings. The CUBs function
as utility suppliers to the three projects.
Crews will also upgrade a deionization water plant and a high
efficiency reverse osmosis plant to filter out chemicals used
in the manufacturing process. When the project is completed,
the fab will use the same amount of water, but with 50 percent
more production capacity.
"They use a lot of nasty stuff, but by the time it goes
through the system, it's abated, said Jim Beals, Sandia project
manager. "Everything is scrubbed or chemically treated."
The micro-lab is composed of chemical, electrical and laser
labs, along with an education and design center. The lab will
provide space for more than 270 researchers for developing,
prototyping and testing micro-system components.
In the Weapons Integration Facility, the building is designed
with a classified and unclassified area. The classified wing
features a virtual interactive environment workspace, visualization
lab, electrical and laser labs and offices for more than 270
people.
The three buildings will be similar in design, but with differences
denoting their uses.
Architects are aiming for a contemporary design in the project,
which will become the south gateway to Sandia Labs.
"The intent is for the building to reflect what is going
on inside," Maute said. "They use similar materials,
but they don't look like identical twins, but rather members
of the same family."
>Duke City Heats Up
>A Fab Project
>Center of Culture
>A New Castle
>Lofty Ambitions
|