|
Oro Valley
Hospitals - with their life-support systems, miles of medical
gas piping and complex mechanical systems - are among the
most complicated buildings to construct.
Toss in an extremely tight construction schedule, and the
job becomes even more interesting.
That's the case in Oro Valley, Ariz., where the Nashville
office of Bovis Lend Lease is building a new, state-of-the-art
243,000-sq.-ft. hospital in just 16 months. Contractors on
the $85 million construction-manager-at-risk project are aiming
for a November completion. The owner is Triad Hospitals of
Plano, Texas.
|
"It's just a really fast-paced project," said
Brian Frazier, a project engineer with site utility contractor
Granite Construction of Watsonville, Calif. "Those guys
from Bovis are throwing that building up at a phenomenal pace."
Work on the 35-acre site started in July, with contractors
over-excavating 12 ft. of poor soil from the building's footprint.
Contractors removed more than 80,000 cu. yds of sandy soils
and then imported engineered fill to construct a solid base.
"The biggest hurdle was getting the building pad prepared,"
said Bovis Lend Lease Project manager Jason Adams.
Crews are also roughing in utilities for a future expansion
to meet the growing demands of Oro Valley, a booming community
north of Tucson. Tentative plans call for a second patient
tower when the need arises.
"We thought a lot about immediate, incremental expansion,
as well as out in the future, for another patient tower,"
said Linda Marzialo, a resident architect with Charlottesville,
Va.-based project designer Gould Turner Group. "It was
a very important part of the building's design to plan for
a future expansion."
Sitting on a 124,000-sq.-ft. first- floor pad, the four-story,
steel-framed building is topped off with a mechanical penthouse.
Designers barely slipped under Oro Valley's 75-ft. maximum
height allowance with a 74-ft., 10-in. building height. The
three other floors average 35,000 -sq. ft. on each plate.
Plans call for 96 hospital beds on the second and third floors.
The private rooms are 330- sq. ft. each. There will be 18
beds for critical care, 30 beds with telemetry monitoring,
18 rehabilitation beds and 30 general patient beds.
The first floor consists of six operating rooms, four endoscope
rooms, a cath lab, MRI room, a CT room, space for nuclear
medicine and three X-ray rooms, including one dedicated to
the emergency room. The fourth floor is shell space for future
expansion.
Engineers designed special ceiling mounts for 1,000-lb. surgical
booms in the six operating suites. The mounts for the 1,000
lb. booms must be able to take a 7,000-lb. structural moment.
"There used to be hose outlets and electrical connections
in the ceiling or the walls, but now they are using these
articulated booms," said David Ringenberg, a senior project
manager with Ivey Mechanical of Nashville. "The boom
gives the surgeons and the anesthesiologists a lot more flexibility,
and the booms also provide the nitrogen that runs the pneumatic
equipment."
The operating rooms also feature a laminar airflow system
that creates a horizontal airflow to lessen the risk of pathogens.
The project is packed with state-of-the-art technology. The
computer systems are all wireless and the mechanical systems
can be remotely monitored and controlled from owner Triad
Hospitals' Texas office. All patient monitoring is also wireless,
and a pneumatic tube system serves nurses' stations from the
lab and pharmacy. Designers spent $11 million on the mechanical
and controls package.
"It's a pretty high-tech controls package and it was
very expensive," Adams said. "It's the Cadillac
of control systems."
The hospital is designed to the specifications of the new
International Building Code, which placed the project site
in a seismic zone 4, the second- highest seismic rating.
Engineers designed special- moment frames to meet the new
requirements. The steel frames are designed to channel the
force of a seismic event on a horizontal plane, isolating
the force, rather than vertically on the columns.
"Essentially they call it a 'dog bone' because the beam
has a portion of the flange cut out, so it looks like a dog
bone," said structural engineer Mark Hilner, an associate
with Nashville-based Stanley D. Lindsey and Associates. "It
forces any seismic damage into the beam rather than into the
columns, where it could do damage to multiple floors.
"We are creating a zone where we can control what happens
to the building in a large seismic event."
Crews from Little Rock, Ark.-based AFCO Steel erected more
than 1,600 tons of the project's steel frame in just 12 weeks
and supplied another 345 tons of metal pan deck for the hospital's
floor systems. Glenn Van Enk directed the work for AFCO.
Structural Detailing LLC of Brentwood, Tenn., did the steel
detail work.
"We were new to the International Building Code, so we
had to do some different things with the steel than we normally
do," said Brian Cobb, Structural Detailing's operations
manager.
Phoenix-based Hardrock Concrete is pouring more than 7,000
cu. yds. of concrete but will wait to pour the first floor's
concrete slab. Pouring the entire slab in one shot, rather
than pouring the slab and leaving the steel columns open for
later closure creates flatter floors, said Hardrock project
manager Kevin McGrew.
"The good thing is you don't have huge closure pours
on the column, because when you have a monster closure pour,
it makes it harder to get a flat floor." he added. The
building is mostly clad in EFIS, but Cox Masonry of Tucson
is using 15,000 units of natural, dry-stack stone veneer for
architectural accents. Way finding starts at the hospital
entrance, with three different porte-cocheres marking the
emergency entrance, ambulance entrance and visitor's entrance.
The project features high-end finishes throughout, with porcelain
tiling and an art budget that is 1 percent of construction
cost. The exterior EFIS system is three tones of a tan earth
color and the curtain wall systems use a low E, blue-tinted
glass to mimic Arizona's blue sky.
"In terms of the exterior aesthetics, we tried to blend
the hospital in with the community and the natural landscape,"
architect Marzialo said. "We oriented the building to
take advantage of the views of the adjacent Catalina Mountains,
so the patients have a good view."
>Oro Valley
>Green Valley
|