Wired
CCSN Goes Hi Tech
by K. Robert Wendel
Students at the Community College of Southern Nevada will
soon be using the latest in computer technology.
The $25 million Morse Arberry Jr. Telecommunications Building
at the Cheyenne Campus in North Las Vegas will house ultra
modern equipment. The new, two-story, 92,000-sq.-ft. center
is also unique because it is the first public design-build
project in southern Nevada. The procurement method was initially
approved by the 1998 Legislature.
|
After a state-held competition, Martin-Harris Construction
with JMA Architecture Studios won the $14.7 million job in
June. Both are Las Vegas firms.
"Our telecom programs are nationally recognized and in
such high demand that classes are being taught all around
the Las Vegas Valley," Ron Remington, CCSN's former president,
said in a statement. "Bottom line, if this building was
completed and available to students today, it would be completely
full."
Situated on 4.75 acres at the southwest corner of the campus,
the building will be a concrete tilt-wall structure with masonry
block and glass accented by EIFS and limestone veneer. With
87 panels cast onsite, the project will require 4,500 -cu.
yards of concrete.
The largest panel measures 50- ft.- tall by 26- ft. wide,
and weighs 130,000 lbs. It's being used for the stairwell,
which accesses the roof. Set atop spread footings, the 37-ft.-tall
new building contains classrooms, computer labs, administration
areas, conference rooms, and a 2,400-sq.-ft. auditorium.
Additionally, there is a digital animation and video editing
spaces, plus a production studio, tape libraries, and lounge
spaces.
"The new telecom building is a critical step in attracting
high-tech industry and diversifying the economy of southern
Nevada," said Bill Synder, president of the CCSN Foundation.
"Global leaders in telecommunications like Cisco Systems
and Sprint have already invested millions in direct donations
and in-kind goods and services."
Future plans call for an open-air roof-level lab area for
teaching antenna and satellite dish installation. The roof
is steel-framed to withstand live loads.
The building uses a total of 1,000 tons of steel . Wright
Engineers Inc., Las Vegas, provided the structural design.
"The roof slab is 8 in. thick whereas roofs generally
are minimally designed," said Steve Goold, a principal
with Wright Engineers. "It had to withstand the live
load of students as well as anchor antennas."
Named after Morse Arberry Jr., a state assemblyman who helped
secure funds for the project, the new building will connect
to the school's adjacent computer building at the second-floor
via a 60-ft.-long steel canopied bridge supported by four
16-in-sq. columns.
A 200-ft.-long, 35-ft.-wide landscaped pedestrian mall, connecting
the north and south portions of the campus, acts as a defining
gateway entrance.
Due to costly high-tech machinery, the telecom building has
required extensive mechanical and electrical work. The center
is serviced by a 3,333-sq.-ft., single-level central plant
that houses two chillers and three boilers. Southwest Air
of Las Vegas is the mechanical contractor.
The ground-level floor slab is depressed 2.5 in. in order
to house all of the facility's cabling and fiber optics. The
second-floor uses standard cable trays, with wire running
wire through the walls. Ultimately, the configuration gives
the school the flexibility it needs to blend media technology
with computing programs.
GSL Electric of Salt Lake City is the electrical contractor.
The project also utilizes the latest in green building techniques.
For example, there are automatic dimming switches in each
of the rooms. Also, the design-build team is using recycled
materials wherever possible, including everything from insulation
and asphalt to finished woodwork and material fill.
Once completed, the building will seek Leadership in Energy
and Environmental Design certification from the U.S. Green
Building Council as well as an Energy Star rating from the
U.S. Department of Energy.
"The project incorporates day lighting into 75 percent
of its rooms, plus it has very efficient glazing and site
orientation to minimize heat and cooling costs," said
Michael Crowe, JMA's project manager.
Roughly 150 people will be working on the project during the
height of construction.
Scheduled to finish by July 2004, the 12-month project is
currently on schedule. When completed, the building will operate
as a 100 percent wireless network and Internet environment.
"It has been a challenge to work with the congestion
on the campus," said Ron LaRue, Martin-Harris' project
manager. "There is a lot of traffic so we have to coordinate
things very carefully."
The new building allows the college to expand its programs
in fiber-optic communication, computer networking, high-speed
data transmission, satellite transmissions, wireless networks,
television broadcasting and digital media. The college already
operates one of the largest Cisco Networking Academy Training
Centers in the United States.
>Wired
>ABQ Gym
>Phoenix
Library
|