|
A 'Green' Use for an Old Gym
by K. Robert Wendel
When Albuquerque High School shut down in the early 1970s,
the cheers in its gymnasium gave way to silence - and occasional
vandalism.
Now, there's something to cheer about again in the old gym.
The structure is being redeveloped under "Green Building"
guidelines into upscale condominiums part of a larger project
that is creating a rebirth in the once- rundown area.
"The nature of historic preservation certainly lends
itself to green building. The idea of reuse one of the key
principals in green building," said Amber Kennington,
chief operating officer of developer Paradigm and Company.
|
"Along those lines, we felt like going ahead and upholding
the intent of green construction. A L.E.E.D. certified building
was something whose time as has come."
Albuquerque's Paradigm and Company and Richardson and Richardson
Construction completed the restoration of the old Albuquerque
High Classroom building in February into apartments, and a
slew of new live/work units on Arno Street are adding critical
mass to the area's redevelopment.
Paradigm and Richardson and Richardson are teaming up again,
along with local architect Dekker/Perich/Sabatini, to renovate
the 64,000-sq.-ft. gymnasium under Leadership in Environmental
Engineering and Design guidelines.
"Quite a bit of the efforts in L.E.E.D. certification
are in the materials and resources and that includes building
reuse," said architect Ashley Burkholder of Dekker/Perich/Sabatini.
"We are getting the bulk of our points in materials and
resources, with a heavy component of indoor environmental
quality."
Burkholder said that in addition to high- efficiency mechanical
systems, the condo's homeowner association contract calls
for no smoking in the building, even in individually owned
units.
Fifty-four condominium units are being created in the old
gym, ranging in size from 650 to 1,300 sq. ft. Unit prices
have not been set. The project's construction value is $6
million, and the job should be completed in February.
Designers employed a cooling tower to keep the units cool,
along with high- efficiency heat pumps controlled individually
from the units. Existing clerestory windows will be operable,
allowing cross ventilation. The windows also provide a large
percentage of natural day lighting, another L.E.E.D. design
component.
A continuous- pump boiler provides hot water directly to the
plumbing fixtures, which are all low flow. The continuous
pump cuts down water wasted while waiting for the hot water
to flow.
Other "green building" techniques included recycling
demolished concrete and steel, and recycling construction
waste on site. The contractor said the efforts didn't result
in much extra cost.
Contractors are also refurbishing and reusing as much of the
original building as possible, including the old windows.
"A big point was the reuse of existing parts of the building,"
said project manager Mark Carroll of Richardson and Richardson
Construction. "We are refurbishing all the old windows
and putting double-pane, low E glass. It gives the same properties
as triple- pane windows, but in a double- pane assembly."
The main gym area will see 20 new units in two levels and
10 units in the former cafeteria. Other units are tucked into
the wrestling room, music room and girls gym. In the gym,
a 30-ft.- wide corridor runs down the center of the basketball
court, flanked by units on both sides.
The original wood bleachers are being retained in the gym's
bleacher section, with split-level units flanking them. The
second- floor units also feature interior mezzanines with
the original exposed steel trusses.
"We are going with the spirit of the area in rebuilding
downtown, and that's why we left the bleachers,""We
are going to keep the bleacher intact, so it looks like it
always did and gives you a pretty good feel for what this
once was," said architect Joe Boehning of Dekker/Perich/Sabatini.
A steel frame riding on footings below the cafeteria supports
the new units in the gym and creates a difficult erection
situation. Contractors must somehow slide the steel beams
through holes in the gym floor without the use of cranes or
heavy machinery.
"We are going to cut holes through the floors, drop the
steel columns and get them brace framed, but we have to miss
all those concrete beams in the cafeteria," Carroll said.
"There is no opportunity to get any equipment into the
building, so we are going to have to use block and tackle,
king falls and hoists. No cranes."
Ninety tons of new structural steel will be used in the project.
As with any renovation, there are always surprises awaiting.
Crews hoped they could keep the old original gypsum plank
underneath the roof sheathing, but they found years of moisture
damage to the roof, so the gypsum had to be replaced with
steel sheathing. The building will be capped with an insulated,
standing- seam metal roof.
"The gypsum is so porous it just sucks the moisture in
there," Carroll said. "There was a tremendous amount
of water damage on the perimeter or those planks, and the
center mesh was completely rotted out. It really caught us
with our pants down."
>Wired
>ABQ Gym
>Phoenix
Library
|