|
Phoenix Library
by K. Robert Wendel
The city of Phoenix is embracing green building at its new
$2.6 million Desert Broom Library.
The 15,000-sq.-ft. high-design project follows numerous Leadership
in Environmental Engineering and Design requirements, including
the use of recycled lumber, wood certified by the Forest Stewardship
Council and on site recycling of trash and materials.
"The city is really trying to be pro-active in the green
build arena," said project manager Art Jordon of Phoenix-based
Linthicum Constructors Inc. "Phoenix is trying to be
on the leading edge of energy efficiency."
|
Built on an isolated foundation, the new library sits under
a giant floating roof that not only encloses the library but
also provides shade for a 10,000-sq.-ft. outdoor reading patio.
Fifty randomly placed steel columns support recycled wood
beams, which are capped off with a built-up roof system. The
steel columns are naturally rusted and covered with a clear
coat, eliminating the need for paint and lowering volatile
organic compounds.
The columns sit on 55 caissons 2- ft. in diameter. and drilled
6- ft down.
"The building acts like a nurse tree, with other trees
growing up in the shadows," said project architect Steve
Kennedy of Phoenix's Richard and Bauer. "The columns
represent randomly spaced trees to give a natural look, like
trees coming from out of the desert."
Linthicum Constructors started work on the construction-manager-at
risk project in November. The anticipated opening date is
in October.
The project sits on a master- planned 35-acre parcel at Tatum
and Cave Creek roads that was mostly virgin desert. A 96-space
parking lot and a city park are also planned for the site.
Designers and contractors want to preserve as much of the
natural vegetation as possible. Site fences are just a few
feet from the building perimeter, so workers don't disturb
the desert.
"For the most part, we are trying to blend in with the
existing desert," said civil engineer Mike Jackson of
Phoenix-based KPFF Consulting Engineers. "The architect
wanted to maintain the rural feeling so the building wasn't
sticking out of the desert."
On the library's side facing Tatum Boulevard, a plywood sheer
wall gives the mostly glass building sheer strength. There
also are limited runs of masonry walls. The plywood sheathing
will be covered with translucent "polygal" panels.
The other three sides utilize glass curtain walls to provide
daylighting and limit the use of electric lights. The project
has a complicated electrical system, with all the space in
the elevated floor system required for data wiring.
"We couldn't run anything in the elevated floor space
and most of the ceiling was open, so we ended up stubbing
300 to 400 penetrations from underneath the slab," said
Ted Wilber, a project manager for Scottsdale-based JEN Electric.
"The city librarian felt he needed as much room as possible
for data (cables) down the road, so we had to keep everything
under the slab."
Much of the library's lighting comes from glass curtain walls
and skylight cut outs in the roof. The three skylights feature
large translucent cubes that descend from the ceiling. Plans
call for using the cubes as projectors to view various images
and media. "There are very few walls, but the L-shaped
masonry walls are the shear walls that hold up in case of
an earthquake," said structural engineer Richard Smith
of Phoenix-based KPFF Consulting Engineers. "We used
drag straps (long beams with tie straps) to transfer the load
from the main roof around the skylights and anchored them
to the masonry walls."
Both the mechanical and electrical systems were designed under
L.E.E.D. guidelines. The library features high-efficiency
roof-top package units, which combined with the building's
natural shading, should help out on electric bills.
The building doesn't use much ductwork, which cuts down on
fan electrical load and reduces the friction load required
to push air through the ducts.
"We are trying to make a building that is very efficient
from not only an energy standpoint, but also from a renewable
resource standpoint, but still make it usable for an owner
on a tight budget," said Monte Sturdevant, president
of Energy Systems Design Inc. of Phoenix.
Concrete with a 25 percent composition of fly ash was another
L.E.E.D. component used in project construction. Crews from
Glendale, Ariz., based JEC Contracting Corp. poured more than
400 cu. yds. of varying colors and shades of concrete.
"There's quite a variety of concrete," said Jerry
Everett, a project administrator for JEC.
"It's a very unique project with a lot of exposed aggregate,
ground concrete and colored concrete."
This isn't the only "green" library Phoenix is building.
The city recently tapped Tucson-based Line and Space Architects,
along with Linthicum Constructors, for the new, 25,000-sq.-ft.
Caesar Chavez Library in south Phoenix.
"We are looking at green building on a project-by-project
basis," said city architect Jon Kolstad. "Our main
concentration is in air conditioning and heating, so we are
putting the most efficient systems we can possibly buy into
our building and looking at the long-term payback."
>Wired
>ABQ Gym
>Phoenix
Library
|