Features
 Current Features
 Past Features





ADOT - June 2004

I-10/I-19 Interchange
by Alan M. Petrillo

After 10 years, the enormous undertaking of rebuilding the interchange between two busy southern Arizona interstate freeways-with minimal traffic disruption-is nearing completion.

Known as "the Crossing," the $54.3 million traffic interchange project in Tucson connects Interstate 10 to Interstate 19 on three levels, using 10 bridges and eight ramps. The first designs for the roadways were put to paper a decade ago.

advertisement

Bill Dehn, project manager for URS Corp. of Tucson, the project engineers, said the job took huge quantities of materials, including:

  • 1.4 million cu. yds. of embankment
  • 72,000 tons of bituminous asphalt pavement
  • 68,000 cu. yds. of Portland cement concrete pavement
  • 6.1 million lbs. of reinforcing steel
  • 9,000 -lin. ft of drilled shafts
  • 41,000 cu. yds of Portland concrete cement for the bridges

    "Everything pretty much worked according to the plan," said David Estfan, project manager for Pulice Construction of Phoenix, the general contractor on the job. "We try to anticipate the unusual circumstances on a job because we have to do things within certain time periods. "

    Still, there still were difficulties to overcome, Estfan said.

    "On an intense project of this size, just getting done on time for the various phases is an obstacle," he said. "It's especially difficult on a job like this where bridges have to go up and traffic switches have to be coordinated."

    Estfan added that traffic on the two interstates and the connection between them had to be rerouted several times in order to take down the existing bridges and construct the new ones.

    "We had to handle the bridges without impeding traffic on the two roads," he said.

    Because of the heavy traffic on the two interstates, two lanes were generally maintained in each direction on each road throughout the project.

    The old interchange had a number of deficiencies that were remedied by the redesign, including a very tight radius on the ramp from I-19 north to I-10 east, as well as a loop ramp from I-10 west to I-19 south.

    Site issues also included acquired property on which there had been a history of wildcat dumping.

    "There was plenty of buried debris, garbage and trash that had to be cleaned up, and a high concentraction of lead at one location near Julian Wash," Dehn said. "Also two slaughterhouses had been located in the area years ago."

    There also were archeological issues.

    Investigations into the numerous archeological sites in the area began when the project engineers were 15 percent into the design state, Dehn said. "We did a lot of work to clear the site before construction began," he added.

    Dehn said the Julian Wash once ran through the area before the Tucson Diversion Channel diverted its flow.

    "There were the remains of many pit houses and artifacts around the Julian Wash," he said. "Those areas were fenced and preserved so that construction equipment couldn't damage the sites. Where possible we did a full recovery of any artifacts in cooperation with the Arizona Historic Preservation Office."

    The cost of the archeological portion of the contract was $1.2 million.

    Estfan said none of the archeological sites impeded the work on the roadways.

    "The archeological team did a fine job before we (Pulice) got on the site with our equipment," Estfan said. "They had dug their trenches, marked out and fenced many areas that contained artifacts or cultural sites. We knew where the designated areas were and stayed away from them."

    Estfan said he believes the interchange project went smoothly because of close cooperation among his firm, URS and ADOT.

    "Both the design engineers and the state have been a lot of help with the issues that came up during construction," he added. "Nothing lagged because there were quick resolutions to the issues. I put that down to people who were very open to ideas and good at communicating."

    The project has received positive community feedback, according to Ana M. Olivares, resident engineer for Arizona Department of Transportation, Tucson District Construction.

    She said the project maintained a Web site and information line throughout the construction phases, and also issued brochures, public service announcements and construction alerts.


    >ADOT Overview
    >Where the Rubber Meets the Road
    >Connecting the Communities
    >I-10/I-19 Interchange
    >Hoover Dam Bypass - Nevada Approach

  •  Click here for more Features >>


     


    Sponsors

    © 2008 The McGraw-Hill Companies, Inc.
    All Rights Reserved