|
Albuquerque Presbyterian Hospital
by K. Robert Wendel
"Quiet, please," was a bit harder for Bill Schuttler
to obey than for the ordinary visitor to a hospital.
Schuttler is the overall project manager on the $55 million
construction and renovation job for Albuquerque's Presbyterian
Hospital, the largest acute-care hospital in New Mexico.
The work, a joint venture for the Southwest and Midwest divisions
of McCarthy Construction, includes a three-story addition
of 150,000 sq. ft. and 25,000 sq. ft. of renovation. It required
coordinating the services of 12 subcontractors.
|
The hospital is on Central Avenue, just east of Interstate
25.
As Schuttler's crews drilled 75-ft.-deep auger-cast piles
inside the existing facility to support additions that would
rise above it, they had to work around a continual influx
of patients and not disturb vibration-sensitive equipment
such as CT scanners and MRI.
The crews also upgraded existing steel support beams to meet
new seismic codes, demolished part of the building's existing
brick skin, added three new elevators and raised four existing
ones.
"We could only work at certain times because of the noise,"
Schuttler said "We put up sound blankets, moved patients
away, and used dust partitions and HEPA filters."
To drill one pile, crews removed a section of existing roof
to gain the vertical space needed to operate the drilling
machine. Another hole, inside the hospital's main lobby, was
drilled by relocating the patient entryway and using a small
drill rig.
Pressurized grout was pumped down and a reinforcing steel
cage stabbed into the wet material.
"The concrete goes into square footings that sit atop
the piles," Schuttler said.
L.G. Barcus and Sons drilled the holes.
Earl Brooks, superintendent for Klinger Construction of Albuquerque,
a subcontractor on the job, said that additional hoses were
needed to route concrete so as not to interfere with hospital
operations.
"There were times we were asked to stop because we were
making too much noise for a patient, so we stopped,"
he said. "It added some cost, but if it wasn't too bad,
and we just absorbed it."
To upgrade in-place steel supports, the crews took pictures
of existing areas to be sure they could re-create what they
were about to destroy. Workers broke down walls and stripped
insulation from existing 14-in. to 18-in.-thick columns before
welding .5-in. to .75-in. plates to them.
Because of the new seismic requirements, technicians had to
perform load tests on the steel beams to ensure they would
support the mandated load limit. Crews from AMFAB Steel also
ripped out walls to install K-braces and chevron braces built
from 8-in. to 10-in. tube steel to stiffen the frame further.
More than 1,300 tons of steel will be used during construction.
"It's a five day process for each room," said project
manager Tim Tyree of Albuquerque-based AMFAB Steel. "The
contractor gets two days to go in and strip the walls, we
have one day to install the stiffner plates and then two days
to close it back up."
Software allowed AMFAB designers to totally construct the
steel portion of the job digitally, engineering and detailing
the project without even using a pencil. All of the information
for cutting and drilling is programmed into a computer, resulting
in more efficient and quicker designing.
The beams were then re-fireproofed and the walls rebuilt.
Only four vertical steel girders support the entire new section,
Schuttler added.
"Everything else is tied to that."
A two-hour firewall space separates construction and user
areas. Passage of fire through the chamber would be retarded
by mineral fiber.
Special features include Corian surfaces instead of laminated
countertops.
"You chip plastic and it delaminates," Schuttler
said. Plastic's hard to repair and doesn't hold up well in
institutional facilities."
The Corian is hard enough to be used in a continuous-appearing
surface for countertop and sinks, which means no additional
material need be imported and affixed for basins. Sinks are
built separately and then glued in place, to provide the seamless
appearance.
Steve Zediker, project manager for ISEC Inc. of Mesa, Ariz.,
which provided the Corian fixtures, said the material is resin-based
and comes anywhere from .25 to .75 in. thick. Half-in. thickness
was used at Presbyterian.
"Unless you burn it, it won't wear out," Zediker
added. "If scratched, it can be sanded. It's the same
all the way through."
The material is applied to plywood for its base.
Cabinets are of raised-face maple panels, for style and because
they'll last longer, Zediker said.
The HVAC system engages air handlers in the roof penthouse
that serves each floor.
"Actually, half a floor," Schuttler said. "The
requirements are different in each half for isolation rooms,
emergency, post-partum rooms, and so on." The system,
managed by Trane Control Systems, uses variable- speed drives
controlled by temperature and pressure sensors.
The service elevators, by Thyssen-Krupp, use a card access
system only available for employees.
Landscaping consultant Sites Southwest Landscaping oversaw
work on an inner courtyard, as well as landscape replacement
for the materials staging area.
According to Pat Gay, project landscape architect, and Chad
Depugh, landscape designer and construction inspector, more
and more hospitals "are recognizing the value of having
small outdoor areas for people to get away."
A boom crane, with bucket removed, lifted 10-ft.-tall trees
over existing walls by using nylon straps made into a cage
and strapped to the root balls. Hawthorne and Eastern Redbird
flowering ornamental trees were among the most visible landscape
imports.
The renovation project began in March 2002 and is slated for
turnover to the owners in July. It is on time and on budget.
"The owner was very happy with the way we put things
together," Schuttler said. "It was nondisruptive.
The floors are very open and clean, the colors bright. It
doesn't look like a hospital to me."
>Healthcare
Overview
>Specialty
Hospitals
>Carson-Tahoe
Regional Medical Center
>Albuquerque
Presbyterian Hospital
>Banner
Estrella Medical Center
>Scottsdale
Osborn Medical Center
|