|
Downtown Rising
Civic Center Adds to Critical Mass
By K. Robert Wendel
Construction is under way on a massive new convention center
that promises to reshape downtown Phoenix and vault the city
into a prominent destination point for meetings, trade shows
and conventions.
Work on the $600 Phoenix Civic Plaza started last fall with
site preparation. Plans call for 2 million sq. ft. of new
and remodeled convention space to be open by mid- 2009.
The project consists of a new west building, new north building
and a renovation of the south building.
|
"All the existing square footage will stay in place
until the west convention hall opens," said Claude Swartwood,
the project manger for the city Phoenix Civic Plaza. "Then,
we will take >> down the existing north convention center,
which leaves us with the same amount of space while we build
the north convention center."
Plans are to release a core and shell package in June for
the first convention hall.
Work is also set to begin on the renovation of the nearby
Symphony Hall this summer.
"It's a seperate contract, but all part of the same job,"
said Hunt Construction Group contract manager Bob May. "There's
a lot of interior renovations at Symphony Hall, along with
mechanical and electrical, as well as some asbestos and lead
abatement." ADA compliance issues will also be addressed.
The west building is the first to open in 2006, followed by
the north hall in 2008 and the south convention remodeling
in 2009. Phoenix voters approved $300 million in funding for
the project with the state of Arizona committing another $300
million.
"The convention center is the lynchpin for a lot of redevelopment
in the downtown," said Scott Sumners, civic plaza deputy
director. "Combined with the residential development,
Arizona State University's commitment to downtown and the
light- rail project, this will spark downtown and provide
a lively, 24-7 environment."
The new convention center is one of the largest vertical construction
projects in Arizona history and it is also the largest "green"
building effort in the United States. The construction team
is aiming for a "Leadership in Engineering and Environmental
Design" designation from the U.S. Green Building Council.
Some "green" techniques under discussion include
installing solar panels. Energy conservation and using recyclable
materials are also key features.
The new project more than triples the size of the existing
convention center, which is now the 67th largest convention
hall in the United States. When the project is completed,
the new convention center will be among the 20 largest convention
centers. Sumners said about 120,000 people use the existing
hall each year, with projections showing an estimated 345,000
users when construction is completed.
He added that each conventioneer spends an average of $1,500
during his or her stay, making a sizable impact on the local
economy.
The city awarded a construction- manager- at-risk contract
after reviewing 11 submissions on the design side and eight
submissions on the construction side. It settled on the tri-
venture group of Hunt Construction of Phoenix, Alvarado Construction
of Denver and Russell Construction of Atlanta.
The contractor has committed that 20 percent of the project
must go to minority or women-owned businesses.
The project features a host of engineers, including Phoenix-based
LSW Engineers Arizona Inc., Paul-Koehler Structural Engineers,
David Evans and Associates, both of Phoenix and Los Angeles-based
Syska Hennesy.
Both designers and builders are facing a daunting task. Contractors
must excavate millions of cubic yards of earth for the project,
which sits 45- ft. below grade and rises 10 stories above
grade. BCS Enterprises is the excavation contractor. In addition
to excavation, thousands of cubic yards of concrete must be
trucked into the site, which sits in the busy downtown of
America's fifth largest city.
"Everything about this project is large," said Patrick
Edwards, the project manager and a principal with the local
Phoenix office of Leo A Daly. The firm is sharing design duties
with Kansas-based HOK Event and Westlake Reed Leskosky of
Phoenix. Most of the convention space sits 45-ft. below grade,
with the new west hall eventually connecting to the east hall
under Third Street, creating 600,000 sq. ft. of contiguous
convention hall space. Monroe Street is slated to become the
haul road in and out of the convention basement.
The bays between columns are 120 -ft. by 90 -ft., with a 35-ft.-
tall ceiling. Four other levels feature meeting rooms on the
at-grade level, conference rooms on the third, administration
on the fourth and a multi purpose space on the fifth.
The project will feature a high-tech communication and multi-media
system, with plans calling for a central utility corridor
to run underneath the below-grade convention hall.
The four above-grade levels sit on massive steel beams with
808 -ft. lbs. of load for every foot of steel beam.
Rapidly rising steel prices forced designers back to the boards
for some value engineering. The first phase of the project
calls for more than 7,500 tons of steel. The entire project
will use approximately 25,000 tons.
"Steel is a big issue because of the rapid acceleration
of prices, so it's a big cramp on the project," Edwards
said. "We had to go back and do some rigorous optimization
to bring the costs back into line."
The city will temporarily abandon Third Street while contractors
open a cut to construct the connection between the east and
west halls. The street's future is still under discussion,
with one proposal calling for a pedestrian street without
auto traffic.
Washington Street also gets a make over and loses its dip
under the existing convention center, which will be demolished.
Keeping the massive convention center pedestrian friendly
was a key objective for designers. At the street level, plans
call for retail shops and offices along the perimeter of the
building. At the main entrance, a soaring 70-ft.- tall glass
curtain wall opens into an air-conditioned atrium that is
110 -ft. tall. The street level features sandstone accents,
but a theme for the entire project hasn't been decided.
"We are trying to engage people at the street level,
even if they aren't going into the convention center,"
said Nirmal Mangal, a vice president at Leo A Daly.
To keep the atrium cool in the summer, architects employed
steel shades that cut the heat load but allow natural light
in. On the west side of the east hall, roof beams cantilever
70-ft. out to provide shading, with another 70-ft. of shading
cantilevering over Third Street from the west hall.
"The architects have paid a lot of attention to sun and
shadow," Sumners said. "We are excited by the design
because it's not a building you would find in Pittsburgh,
Connecticut or even Texas. It's unique to Arizona."
>Phoenix Market Holding its Own
>A Friendly Place to Retire
>Downtown Rising
>Riding the Rails
|