|
River Remedy
Work Continues on Hoover Dam Bypass
By Tony Illia
Significant drilling, blasting and embankment work are under
way on the Nevada side of the $235 million Hoover Dam Bypass
Bridge.
The progress comes none too soon.
A need for another route over the Colorado River dates back
to the 1960s. As it stands, the two-lane U.S. Highway 93 over
the dam is a major commercial corridor identified in the North
America Free Trade Agreement between the United States, Mexico
and Canada. But since Sept. 11, truck traffic over the dam
has been rerouted 23 mi. away, costing the industry an estimated
$30 million annually.
|
The Federal Highway Administration is fast-tracking construction
by awarding two of the four contracts needed to complete the
1,900-ft.-long, four-lane bypass bridge, which also includes
4.3 mi. of accompanying roadway.
Edward Kraemer & Sons Inc., of Plain, Wis. is performing
the $30.1 million Nevada approach, while R.E. Monks Construction
Inc., of Fountain Hills, Ariz., and Chino Valley, Ariz.-based
Vastco Inc., are building the $21.4 million Arizona approach.
A consortium led by HDR Inc., of Omaha, Neb., Jacobs Inc.,
of Pasadena, Calif., and San Francisco-based T.Y. Lin International
is serving as the project's architect/engineer.
"There are significantly more constraints and logistical
challenges to the Nevada approach," said Dave Zanetell,
the Highway Administration's project manager. "There
is more volume in terms of material and structures."
The 2.2-mi.-long Nevada approach stretches from U.S. 93 to
the new Colorado River Bridge crossing, approximately 1,500
ft. downstream of the Hoover Dam. It includes a new asphalt
roadway with two lanes in each direction divided by a concrete
median.
There are also five new bridges, including a 465-ft.-long,
cast-in-place box girder structure with a 12-ft.-tall, 24-ft.-wide
wildlife crossing underneath.
The project requires a total of 1,500 tons of reinforcing
steel to complete.
Kraemer is additionally building a diamond interchange just
east of the Hacienda Hotel Casino to provide access to the
existing U.S. 93, which will become the Hoover Dam access
road.
The most impressive bridge is a 463-ft.-long, three-span,
steel-girder structure that crosses over a 160-ft.-deep ravine.
Mike Motil, Kraemer's senior project manager, said a 300-ton
crawler crane with 200 ft. of lattice boom must be moved to
the bottom of the ravine. It will be used to help place the
supporting piers, abutment caps and structural steel.
Meanwhile, two hydraulic truck cranes will be used at either
end of the span to help position the steel and bridge decking
into place. To achieve the right angle for construction, Kraemer
shaved 150 ft. from one of the canyon walls.
The rugged topography of tuff and basalt rock has resulted
in some difficult excavation. KLB Construction Inc., of Lynnwood,
Wash., is performing $12 million worth of excavation, drilling
and blasting. The work must occur in a piecemeal fashion,
carefully carving out the mountainside to correct the depth
and pitch.
The material is being screened and used for 50,000 sq. ft.
of mechanically stabilized earth retaining walls, averaging
20 feet. high, along the highway.
"There are approximately 1.6 million cu. yds. of excavation,
said David Lingle, KLB's project manager. "There are
six drills on the job, plus five 60-ton rock trucks, two articulated
rock trucks and four excavators."
Other contract work calls for a small extension to the National
Park Service's river mountain loop trail, plus various storm
drainage structures. About 4.5 mi. of 7-ft.-tall game fencing
will be installed to protect natural wildlife such as the
big horn sheep and desert tortoises in the area.
"Kraemer & Sons have played an important part in
getting the overall bypass started," Zanetell said. "The
Nevada side is a real challenging job in terms of phasing
and scheduling, but [Kraemer] has been real strong in paying
attention to those details."
Kraemer expects its workforce to peak at 60 people, finishing
the project well in advance of its October 2005 deadline.
Funding delays from the reauthorization of Transportation
Equity Act for the 21st Century, the federal road and highways
bill that expired last year, has pushed back the bridge's
final completion date to 2008.
>NDOT Overview
>River Remedy
>Spaghetti Bowl
|