|
Taj Ma Garage
New Maintenance Facility in Store for Glendale
By K. Robert Wendel
Dave Harvey is a busy guy. The city of Glendale, Ariz., superintendent
of equipment management has 1,400 trucks, tractors and other
pieces of equipment to maintain.
For the past 20 years, his department has made due with a
small, out-of-date facility that often left mechanics lying
on hot asphalt in August while repairing equipment.
Now, Harvey and his staff are eyeing their new home, a 70,000-sq.-ft.,
state-of-the-art maintenance facility under construction by
DL Withers of Phoenix. John Norbut is Wither's project manager
and Pat Peters is one of two superintendents.
|
"To get people out of working outside and to give us
adequate space, it's pretty exciting," Harvey said. "We
are ready to go as soon as they open the doors."
Those doors opened this month. In addition to the shop space,
the facility has a two-story, 24,000- sq.- ft. parts warehouse;
10,000 sq. ft. of administration; two wash bays; and a tire-
changing shop; and welding and auto body shops.
The project is being built under a construction manager at-risk
contract, which city engineer Bill Passmore said "is
a little easier on everyone than a design-bid-build project.
We think we get a much better product in the end."
Work on the $16.8 million project started in August 2003 with
earthwork at the 40-acre site on Grand Avenue near downtown
Glendale. Design on the project started a year before, with
meetings to determine the best shape and form of the project.
"One of the reasons the design process took longer is
that we had to make sure we were providing the right set-ups
for vendors and equipment manufacturers," said Mike Thomas,
a project architect with Arrington Watkins Architects of Phoenix.
"We had several meetings to discuss the scope and type
of construction, so we went through several alliterations
before we finally got what we wanted."
A barrel-vaulted roof, evoking the appearance of a blimp hanger,
tops the tilt-up project, which uses 35-ft. tall concrete
panels. The high ceilings allow mechanics to pull large hydraulic
cylinders from city trash trucks and allow the use of 2-ton
and 5-ton bridge cranes.
"When you start adding up all the factors they need,
you end up with a very large structure and the question becomes
'how do you efficiently span that space that is both elegant
and cost- effective?" said Mike Quinn, associate architect
with Arrington Watkins Architects.
"We also needed to get light down into that space to
try and make it a nice work environment."
Structural designers used 100-ft. long, 50-ton steel trusses
on 20-ft centers to span the mechanic bays.
Designers pierced the acoustic structural steel deck roof
system with ribbon skylights throughout the two major service
bays to provide natural lighting. The acoustic panels deaden
noise transmission.
The project sits on a slab-on-grade foundation with slab thickness
at 12 -in. in the service bays and 5 -in. in the administration
areas. Suntec Concrete of Phoenix was the concrete subcontractor.
The bays are divided between light- duty equipment such as
trucks and cars and heavy-duty equipment, such as front-end
loaders and large tractors.
The drive-through mechanic bays are grouped in units of two,
sharing common equipment and computers. Cold air from evaporative
roof coolers is piped down to the shop floor to help cool
mechanics during the hot summer months.
Although the project is located in a busy downtown area, contractors
came into work one day and found a small surprise: a red fox
had made its way to the roof.
DL Withers superintendent Tom Harmeyer tried to corner the
fox and summoned animal control officers, but the fox had
other ideas.
"He ended up jumping off the roof right into where they
were finishing some concrete," Harmeyer said. "The
finishers were pretty surprised to see a fox come flying out
of the sky."
The fox got away.
>Taj Ma Garage
>Jail House Rock
|