|
Water Relief
By Tony Illia
Southern Nevada attracts 8,000 new residents a month and
is one of the country's fastest growing regions. North Las
Vegas and Henderson were the nation's second- and third-fastest
growing cities from April 2000 to July 2002, according to
the U.S. Census Bureau.
All that growth means an added demand for water.
To keep up, the Southern Nevada Water Authority is expanding
its raw- water pumping system at Saddle Island, Lake Mead,
which supplies 81 percent of the Las Vegas Valley with drinking
water. Raw water is drawn from Lake Mead and then filtered
and disinfected at either the 33-year-old Alfred Merritt Smith
Water Treatment Plant or the 2-year-old >> River Mountains
Water Treatment Facility. It's then pumped throughout Las
Vegas Valley via a 100-mi.-long pipeline network.
|
MMC Inc. of North Las Vegas, is currently performing a $32
million raw- water pumping expansion that will enable the
River Mountains Facility to double its treatment capacity
from 150 million gallons of water a day. Scheduled to finish
Oct. 15, 2005, the project entails placing 10 vertical, 4,000-horsepower
pumps at the Saddle Island Pumping Station, plus 12 horizontal
pumps at two booster stations that will carry the water onto
the River Mountains plant.
"This phase will bring the treatment capacity of River
Mountains up to 300 million gallons a day," said Gina
Nielson, SNWA's engineering manager. "This capacity,
as well as the 600 million gallons a day at the Alfred Merritt
Smith Plant will meet the valley's demands through 2025."
At Saddle Island, MMC must modify the existing facility by
demolishing 10 existing shaft wells and rebuilding them 100
-ft. -deeper. A 50,000-lb. overhead crane will be used to
lift and lower the pumps into place, with the heaviest piece
weighing 38,000 lbs. MMC will additionally install a 120-ft.-long
by 20-ft.-tall surge tank that will capture water back flow
in case of a plant shut-down. Acme Electric, North Las Vegas,
is performing the pump wiring.
"The tricky part will be installing the last pumps due
to the confined space inside the station," said Eddie
Urioste, MMC's project manager. "The project will have
about 30 people working onsite at the height of construction."
The project also calls for placing six 3,000-horsepower horizontal
pumps at a booster station across from the Alfred Merritt
Smith plant as well as six 4,000-horsepower horizontal pumps
at the boosting station near Lake Las Vegas in Henderson.
The added capacity propels the raw water from Lake Mead onto
the River Mountains Water Treatment Facility, where it's treated
and distributed throughout the Las Vegas Valley. Montgomery
Watson Harza, of Broomfield, Colo. and CH2M Hill Cos. Ltd.
of Denver, are the joint-venture project engineers under the
name MW/CH2M Hill.
"The initial pump stations were built a few years ago,
but this brings them up to full capacity," said Ted Davis,
project engineer with MW/CH2M Hill.
Pump installation will require six full shutdowns - ranging
from two weeks to one month - at the pumping and booster stations.
Contractors Cargo Co. of Compton, Calif., will transport the
pumps in a single move with a heavy-duty tractor-trailer rig.
The pumps, which weigh a combined 300,000 lbs., must be moved
more than 400 mi. from Salt Lake City to Lake Mead.
The 17-month raw- water pumping expansion is part of SNWA''s
$2.2 billion Capital Improvement Plan, which consists of a
series of infrastructure projects aimed at improving water
quality and reliability. Scheduled through 2017, the program
is funded by a quarter-cent sales tax approved by Clark County
voters in 1998.
|