|
Genome Home
By K. Robert Wendel
A new research institute in the heart of downtown Phoenix
promises to be key weapon in finding the causes and cures
of cancer, diabetes and other diseases, as well as developing
cures for those plagued with disease.
The Phoenix offices of the SmithGroup Architects and DPR Construction
teamed to build the new headquarters of the Translational
Genomics Research Institute and the International Genomics
Consortium, beating six other teams to win the job.
|
"One of the missions of TGen is to translate all of
the discoveries of the human genome project and translate
them into medical applications," said Richard Love, TGen's
chief operating officer. >> "The mission of the
IGC is to disseminate the genomic data on diseases and publish
it so it's available for everybody. Genomic research is the
hottest area in medicine today."
The building's fast-track construction launched in August
2003 with earthwork commencing at the 14.6- acre site at Washington
Boulevard and Third Street. DPR and Smith Group are building
the $45-million, six-story project under a design-build contract
that calls for November occupancy.
"Form follows function," said building designer
Brian Perkins of SmithGroup. "The design of the building
expresses what is going on inside."
The IGC/TGen organizations plan to conduct cutting- edge biomedical
research that capitalizes on the recent milestones in mapping
the human genome.
Scientists and researchers from around the world are being
courted to bring their work to the new building to create
a first-class research center. The project is one of the key
selling points. The city of Phoenix is funding the project
through bonds and will lease the space to TGen/IGC.
"The city of Phoenix wanted a signature, world-class
building to support the research that goes on inside,"
said DPR's project manager Bart Rogers. "The building
is also a recruiting tool to bring researchers to Phoenix."
The complicated project is as much a machine as a building.
Because of the wide variety and types of planned research
that is expected, architects kept the building as flexible
and open as possible. Designers also wanted to avoid venturing
into high-rise zoning, further complicating the need to pack
in as much useable space as possible in the 170,000-sq.-ft.
building.
The Phoenix office of HDR helped the city develop technical
guidelines for the project that outlined the minimum performance
standards for the building.
"TGen and the IGC were somewhat difficult to design because
they are in the infancy and the specific programming needs
weren't there," said SmithGroup project manager Howard
Shugar. "We couldn't design for a specific program. We
had to design for flexible programming that could be adapted
to different uses."
After several designs, architects settled on a cast-in-place
concrete frame with glazed curtain walls, mesh screening and
horizontal and vertical fins that allow plenty of natural
daylighting. The shading limits the amount of direct light
into the interiors, instead relying on reflected light that
is softer.
One of the major design requirements was the need for open
space inside the building. TGen/IGC officials want to encourage
as much interaction between the different scientists as possible.
"The concept of an open lab helped out a lot in design
flexibility," said Russ Healey, a senior mechanical engineer
with SmithGroup. "Everything is built in a modular form
so things can be shifted around."
The exterior concrete uses a special white aggregate to give
the concrete the color of white marble. Crews from DPR of
Phoenix used special plywood forms with an architectural fiberglass
form liners to give an ultra smooth finish. Crews offset the
form seams so seams wouldn't run in a continuous line. All
of the concrete is then caulked and sandblasted. Ceco Concrete
of Phoenix provided the shoring and deck for the elevated
slabs.
The building sits on a massive mat foundation with 28-in.
concrete columns sitting on friction piers drilled 60- ft.
below grade. The concrete columns support 14-in.- thick concrete
decks, with a generous 14-ft., floor-to-floor height. Still,
with the amount of mechanical needs, contractors found the
spaces tight.
"With the building being a testing facility with labs,
we want to have penetrations for the mechanicals through slabs,
and those penetrations needed to be figured out in advance
for special reinforcement," said structural engineer
Jeannie Pfeiffer of Phoenix-based Paul Kohler Engineers. "Vibration
was also an issue because of the research and testing, and
the thick concrete floors were the best solution."
Many of the mechanical systems and ducting were fabricated
off-site by University Mechanical of Tempe then quickly installed.
In just three days, crews installed more than 50,000 lbs.
of ductwork and set the boilers in just one day. The building
relies on a series of centralized mechanical shafts with strobic
fans to eject the building's used air high into the atmosphere.
All of the labs use 100 percent outside air, which goes through
an energy recovery system before getting exhausted.
Preplanning and prefabrication, according to University Mechanical's
Kenneth Tabbutt were the keys to success on the fast-track
job.
"It's paramount to work out a plan before you get in
and commit material dollars and labor dollars," Tabbutt
said. "Some of the benefits of fabricating the components
off- site are that you save logistics and it takes man hours
off the site and puts them in the shop, which is a safer working
environment."
>Genome Home
>Growing Pains
>Betting Big on Bio
|