|
A Landmark of Their Own
By Tony Illia
Landmark Homes and Development, a 24-year-old Northern Nevada
homebuilder, has just finished building its own landmark.
The privately-held firm, which has constructed more than 3,000
single-family detached homes throughout the Truckee Meadows,
recently moved into its new Reno headquarters.
Sacramento-based Panattoni Construction Inc. was the design-build
general contractor and Blakely Johnson & Ghusn Inc. of
Reno the architect-engineer.
"Design-build enables us to custom tailor a project to
meet a customer's needs while better managing costs,"
said Matt Clafton, vice president of construction for Panattoni's
Northern Nevada office. "It also allows us to be the
driving force in a project, hiring the architect and engineer
to work on our time schedule. As a result, everyone is working
as a team toward a common goal."
|
The $5.6 million undertaking entails the design, engineering
and construction of a new three-story, 51,000-sq.-ft. office
building. The project is located in the 2,000-acre, 6,000-home
DaMonte Ranch master-planned community being developed by
Nevada Tri-Partners LLC in southeast Reno.
The concrete tilt-wall structure consists of 33 panels cast
onsite with metal decking over concrete floors supported by
steel joists. The largest panel measures 54-ft. -tall by 18-ft.
-wide and weighs 100,000 lbs. It required a 220-ton lattice-boom
rubber- tired crane to erect. Elko-based Perry Crane and Rigging,
Inc. was the supplier/operator.
The panels average 16-ft. in width with three window openings
measuring 12-ft.- wide by 10-ft -tall. That leaves only 2-ft.
from each panel edge to the opening, which meant casting required
careful placement of reinforcing steel.
Viper Steel of Sparks was the rebar supplier, and Reno-Sparks
Ready Mix Inc. of Reno, provided the concrete. Tedesco Construction
Inc. of Reno was the concrete contractor.With no interior
sheer walls, the exterior panels bear the building's structural
load.
"The windows help to enhance the aesthetic look of the
building, giving it an open feel," said Jeff Turnipseed,
vice president at Blakely Johnson & Ghusn Inc. "They
also serve a practical purpose, bringing natural daylight
into the office areas while providing views of the neighboring
mountains."
A massive glass curtain wall, measuring 67-ft.-wide by 50-ft.-tall,
marks the building's entry. It creates a dramatic sense of
arrival while playing a key role in the building's open feel.
The curved steel-framed entrance façade uses reflective
green-tinted glass.
Meanwhile, the tan-colored panels each have translucent window
openings as well as a checker-board pattern etched into concrete
during casting. The building also has four circular balconies,
with two each on the second and third levels. The balconies
are located at the conference room, employee break area and
executive offices.
The 3.5-acre site, which is in a mitigated wetlands area,
presented some problems.
Roughly 4,000 cu. yards of excavation and imported material
were needed to stabilize the site. Paragon Associates Inc.
of Carson City, a Landmark subsidiary, was the earthwork/paving
contractor.
Landmark's offices will occupy the third floor with Paragon
below. The remainder of the professional space is available
for lease. The building features the latest in high-tech wiring,
and includes a 480-volt back-up generator mounted on the roof
to ensure a consistent power supply.
The building is serviced by a roof top air- handling unit
and boiler system with variable air volume heating and cooling.
Clafton, Panattoni's vice president, said the 10-month project
required 100 tradesmen during the height of construction activity.
It entailed a total of 120 tons of reinforcing steel and 1,500-cu.
yds. of concrete to finish.
>A Pueblo Away From Home
>An Alternative Route
>A Landmark of Their Own
|