|
Building it Big
By Tony Illia
An ambitious sprawling new project is reshaping the southwest
Las Vegas Valley.
EJM Development Co. of Los Angeles, is building a 450-acre,
4.5-million-sq.-ft. mixed-use business park called "The
Arroyo," along the north and south sides of the Interstate-215
Beltway between Rainbow Boulevard and Buffalo Drive in Las
Vegas.
The ambitious, sprawling undertaking is four times larger
than any project EJM has ever attempted and is reshaping the
southwest Las Vegas Valley.
|
Under a cooperative management agreement with the Clark
County Department of Aviation, EJM has a 50-year ground lease
to develop the site. In exchange, the public agency receives
50 percent of the profits.
"We have been developing and refining the master-plan
for more than a year," said Kirk Boylston, EJM's Nevada
regional director. "The Arroyo will have a cohesiveness
of design and layout which will set it apart from similar
projects in Las Vegas."
The $11 million first phase, which broke ground in May, consists
of three single-level concrete tilt-wall industrial/warehouse
buildings, totaling 30,556 -sq. -ft. LM Construction Co.,
Las Vegas, is the general contractor.
Situated on 26 acres between Rainbow Boulevard and Tenaya
Way on the north side of I-215, phase one of The Arroyo is
scheduled to finish in March.
Designed by RGA of Nevada, each double-height structure has
divisibility beginning at 4,000- sq.- ft. The largest structure,
Building C, is a 197,822-sq.-ft. cross-dock facility with
a 30-ft.-high ceiling and an 800-ft.-long by 270-ft.-wide
footprint.
The foundation is set atop a floor slab over 6-ft.-deep spread
footings with a 5 percent slope, which saves on costs. The
remaining two building are 65,934-sq.-ft. with a 20-ft. clearance,
and 44,800-sq.-ft. with a 22-ft.-clearance.
There will be a total of 200 panels cast onsite, with the
largest measuring 32 -ft. -wide by 43 -ft.-tall and weighing
153,500 lbs. AM Concrete Construction, Las Vegas, is the supplier/contractor.
The biggest panel will be up to 8 -in. -thick in order to
withstand the sheer forces of erection. A total of 12,100-cu.
yds of concrete will be used to construct the three buildings
with pours of up to 900-cu. yards at one time. Dielco Crane
Service, Las Vegas, is providing a 300-ton rubber-tired crane
to erect the project's largest panels.
Each building emphasizes spatial flexibility and versatility.
For example, Building C will be supported by 71 steel columns,
measuring 8 -in. -sq. plus 120 -ft. of worth chevron bracing
in the middle. The configuration enables a diversity of floor
plans for large or small tenants on either side with room
for expansion.
The smaller two buildings feature concrete sheer walls at
midpoint that can be removed if needed.
Site preparation was a problem because of solid caliche more
than 8 -ft. below the surface. As a result, Sanders Construction
Inc. of Las Vegas, was hired to blast-out the hard rock with
16,000 sticks of dynamite explosives. Approximately 11,000
tons of dirt was excavated, some of which will be crushed
onsite and used as an aggregate base while other material
will be removed offsite. Las Vegas-based A Grading is the
earthwork contractor.
"Blasting was approximately 20 percent cheaper and faster
than using conventional excavation methods," said Larry
Monkarsh, president of LM Construction. "However, material
prices have increased 10 percent since we bid this project
one year ago."
LM undertook some inventive methods to cut costs, including
negotiating a 1 percent to 2 percent reduction from its subcontractors
for quick payment within 30 days. Also, the contractor pre-ordered
steel, and paid for concrete in advance in order to lock in
prices. The company was eventually able to save up to 6 percent
on the total project amount.
"There will be approximately 150 people onsite during
the height of construction activity," said Don Morgan,
LM's project manager. The firm will self-perform all of its
metal-framing, stud, drywall and painting work.
Scheduled for build-out by 2014, The Arroyo calls for a total
of 1 -million -sq. -ft. of industrial space, 800,000-sq.-ft.
of retail, including both inline and big-box stores, and 1.5
-million -sq. -ft of suburban "Class A" office space.
The remaining space will be build-to-suit structures and custom
pads.
The next phase will consist of three additional concrete tilt-wall
industrial/warehouse buildings, totaling approximately 300,000
-sq. -ft. It will be followed by up to 10 office buildings,
ranging from two to six-stories tall in 2005.
JMA Architecture Studios of Las Vegas provided the master
-planning for the development, which will be tied together
by pedestrian paths, coloring, cohesive buildings and two-lane
divided roadways with landscaped medians.
"This area''s access to McCarran International Airport,
the Las Vegas Strip, and Interstate 15 has quickly made it
a central business district," Boylston said. "With
its I-215 access and location between Green Valley and Summerlin,
the corridor offers an easy commute for employees on either
end of the Las Vegas Valley."
>G-Men Get a New Home
>A vision Reborn
>A Privatized Project
>Building it Big
>Universal
|