|
Streamlined New Baggage Handlers to Speed Travelers
By Tony Illia
Las Vegas' McCarran International Airport was the one of
the nation's first large airports to rebound after 9/11. Fueled
by a growth in leisure and convention travel, McCarran serviced
more than 36 million passengers last year, making it the seventh
busiest airport in the United States. The airport, through
July, has seen a 15.2 percent increase in passenger traffic
over 2003, hosting more than 20 million passengers.
"Immediately after 9/11 we were confronted by two primary
but contradictory challenges: First, to work with the Transportation
Security Administration (TSA) to meet the new standards of
the federal security directives. Second, to implement efficiencies
into the newly created procedures for our passengers,"
said Randall Walker, director of Clark County's Department
of Aviation, which oversees McCarran. "Therefore we are
implementing strategically developed plans to accommodate
an ever-increasing visitor volume and the growing numbers
of traveling residents."
|
Flagship Construction Company Inc., Las Vegas, is installing
a $125 million in-line baggage screening system at McCarran,
that will reduce passenger wait times but still meet new security
concerns. The three-phase, 17-month project involves the construction
of a two-story, 18,000-sq.-ft. expansion north of A/B Gates
Terminal and a single-level, 20,000-sq.-ft. addition to the
south.
Both are steel-framed structures clad with a 1-in-thick insulated
glazing and metal panel skin, housing a combined 10 Electronic
Detection System bomb screening machines. The buildings sit
on drilled caisson foundations, ranging from 30-ft. to 60-ft.
deep and 6-ft. in diameter. The additions are serviced by
two new chillers and air handling units each that are tied
into the airport's central plant. Designed by Domingo Cambeiro
Corp., Las Vegas, the buildings have a similar architectural
theme that matches the airport's existing structures. The
first phase also remodels the 15,000-sq.-ft. satellite cargo
facility, creating new office space and adding two inline
EDS machines.
The second phase entails a two-story 40,000-sq.-ft. stand
alone Terminal 2 building housing more EDS machines. Similar
to the A/B Gates, the second phase is a steel-framed structure
clad with a 1-in-thick insulated glazing and metal panel skin,
on drilled caisson foundations. The machines being installed
use an ultra high frequency Radio Frequency Identification
Detection (RFID) technology that helps ensure all bags are
screened for explosives, a goal of the federal Transportation
Security Administration. Similar technology is being employed
by Wal-Mart and the U.S. Defense Department to track materials.
Matrics Inc., Columbia, Md., and FKI Logistex, Danville, Ky.,
have a $25 million subcontract to place tiny computer chips
on outgoing passengers' luggage tags. Those chips identify
which bags have been screened, their destination and other
information.
John Shoemaker, Matrics vice president of corporate development,
said McCarran will be the first airport to employ the system
and at least six others are waiting in the wings.
"The system helps reduce "the incidence of lost
or mishandled bags while ensuring screened bags are delivered
to the right place at the right time," Walker said. Passengers
won't notice the chips, but they could see a dramatic change
from the current system in which a bag is checked at the ticket
counter then carried by the passenger to the screening point.
On average, 65,000 passengers are screened each day at McCarran.
The third phase consists of two standalone structures, totaling
130,000-sq.-ft. Located near the airport's central rotunda,
the two-story 65,000-sq.-ft. steel-framed buildings have a
metal skin paneling, housing 10 EDS machines apiece.
The project will use three separate teams for each phase,
peaking at a total workforce of 500 people. Flagship will
install 60 RFID and 42 EDS machines, plus 17,435 lin. ft.
of conveyor belt driven by 1,847 individual motors. Scheduled
for completion in September 2005, the project requires 200
drilled caissons, 9,000 cu. yds of concrete and 1,665 tons
of structural steel.
"Much of the work had to take place at night in order
to minimize disruption to the airport's normal operations,"
said Chris Anderson, Flagship's project manager. "Frequently,
we would have only a four-hour window to perform all of our
needed work."
The undertaking has 40 contract milestones with liquidated
damages of up to $10,000 a day. Flagship is self-performing
the drywall, framing, carpentry, painting and fireproofing.
McCarran requires that bidders self-perform at least 15 percent
of the work themselves, believing that it makes contractors
more responsible. Bechtel Infrastructure Corp., a unit of
San Francisco-based Bechtel Group Inc., is the project manager.
>Big Numbers
on a Big Job
>Streamlined
New Baggage Handlers to Speed Travelers
>Tucson
International Takes Off
|