|
Tucson International Takes Off
By Alan Petrillo
It's tough to live with airports and difficult to live without
them.
At Tucson International Airport that image is changing, not
only from the physical viewpoint, but also in the ease of
consumer use.
The Tucson Airport Authority has been involved in an ambitious
project since fall 1999 to update and renovate the 40-year-old
facility, culminating with the current expansion of the terminal,
which handles about 3.5 million passengers a year.
|
Probably the most noticeable change at the airport is the
addition of four barrel vaults that add 70 ft. in depth and
700 ft. in length across the front of the terminal. The total
value of the construction at-risk project is $46 million.
"The most unusual elements of the airport addition are
the canopies in the front," said Robert Tindell, senior
project manager for HNTB Architecture of Los Angeles, the
project architects. "It's quite dynamic how the canopies
stretch out over the roadway."
Tindell added that the design was repeated in the roadway
with smaller canopies extending out from the larger vaults.
Fred Friedl, project manager for the general contractor, Sundt
Construction of Tucson, said the addition will provide 57,000
sq. ft. of new baggage space and 27,000 sq. ft. of ticket
counter space.
"One of the requirements of the job was that we keep
the airport operational, which is why we've been working on
this project for 2.5 years," he said. "We expect
to be finished early in 2005."
The work on the four barrel vaults was done in stages, with
the two center vaults being erected first.
"That was one third of the addition, which we completed
last October," Friedl said. "After we opened that
part, we rerouted the pedestrians through the new vault while
we demolished and then constructed the east and west wings."
Friedl said the east vault should be completed and turned
over to the airport in October, while the west vault should
be completed early in 2005.
The center vault is outfitted with four new tilt-plate luggage
carousels. The east and west vaults will each contain two
more new carousels.
Friedl said a new fiber-optic backbone to handle voice and
data communication was installed in both the addition and
remodeled sections, and that the older part of the building
received six new air handlers and 250 variable- air volume
boxes. The control system also was converted from pneumatic
to direct digital control for more reliability and functionality.
Sundt also is constructing a 200-ft. moving sidewalk on the
lower level to connect the east vault to the newly -constructed
rental car facility, known as the RAC building. Tindell said
the construction period was extended by almost 50 percent
because of the requirement for the airport to continue to
be open for 24 hours.
"Because of that requirement, it's impractical to remodel
everything at once," he added. "So we had to build
the central area like it was a separate building, and when
it was done, we had to do it again for the two wings. This
is typical of most terminal renovations."
When completed, a total of 88,000 sq. ft. of new area will
have been added, and 75,000 sq. ft. of the existing structure
will have been remodeled.
Scott Candrian, president of Sun Mechanical Contracting Inc.
of Tucson, said it has been difficult working around an operating
airport, "especially with all the security requirements
you find there."
He added that while the work has gone smoothly, there was
a considerable amount of coordination necessary in installing
the new mechanical systems and connecting them to the existing
airport building's older systems.
"The complexity comes in when you tie into existing systems,"
he said. "We had to maintain the heating and cooling
systems, so as not to affect the airport operations. There
even were a number of roof drains that had to be rerouted,
but their integrity had to be maintained in case it rained."
Sun Mechanical upgraded the central plant, adding a boiler,
chiller and pumps, and also performed remodeling work in the
existing ticketing and baggage sections.
There was plenty of shift work on the job, according to Chuck
Hughes, project manager for Wilson Electrics Service Corp.
of Phoenix.
"It's challenging to work in a functioning airport and
still keep out of people's way," he said. "We worked
a lot of different shifts, but still wound up crossing into
areas where people were doing their jobs. The scheduling was
very important."
Wilson Electric added electrical service and elements in the
new addition. It also reworked the existing ticketing and
baggage claim sections.
Suzanne McLean, vice president of planning and development
for Tucson Airport Authority, said the project is currently
under budget and running three months ahead of schedule.
"This construction manager at-risk delivery method is
a new experiment for us with a complex project, but we're
quite pleased with the results," she said.
"There have been no disputes, no safety or security issues,
and no public convenience issues."
>Big Numbers
on a Big Job
>Streamlined
New Baggage Handlers to Speed Travelers
>Tucson
International Takes Off
|