| Feeding Growth
By K. Robert Wendel A half-mile concrete
tunnel, significant electrical upgrades and new cooling towers are the major facets
of a $16 million infrastructure upgrade at the University of Arizona in Tucson.
|
Because the university is rapidly expanding its medical research campus with
the addition of three major buildings, and with more on the drawing board, it
was necessary to extend major utilities into the area. Sundt Construction's Heavy
Civil Division, which is based in Phoenix, is the construction manager at-risk
on the contract.
The new U of A buildings includes Drachman Hall (an academic
building), the MRB Building (medical research), and the IBSB Building (research
laboratories.)
Craig Raymond, Sundt's project engineer, said a significant
portion of the project involves relocating existing utility lines in the area
and installing 2,300 lin. ft. >> of precast concrete tunnel, which will
house the "wet" utilities - principally water from the campus central
refrigeration building that will be used for heating and cooling.
"The
tunnel will house high- pressure steam, condensate transfer, pumps and condensate
return and compressed air lines," Raymond said.
The tunnel is trucked
to the site in 20-foot.-long sections, each of which is 5 ft. deep, 6 ft. wide
and weighs 20,000 lbs.
After the tunnel is secured in place, the electrical
subcontractor installs the "dry" utilities - electricity and communications
cables - in ducts laid in a trench beside the tunnel.
Raymond said one
of the bigger challenges Sundt faced was having to keep the streets open during
installation of the tunnel. Sundt pushed 84-in.-diameter steel casing pipe under
five intersections at about 25 ft. deep.
"Each of the pushes was about
60 ft. long," he said. "Under good soil conditions, which we had, we
averaged between 5 and 6 ft. a day."
"The other difficulty facing
us was that there were so many utilities in the ground around these streets that
it would have been difficult to do an open cut on them," Raymond said. "Most
of those lines have been in place since the 1930s and 40s."
Away from
the intersections, the tunnel system could be lowered into open cuts that averaged
8 to 10 ft. to the bottom of the tunnel. Vaults (17 of them) were installed approximately
every 200 ft. to provide access for future pipe upgrades.
Henry Johnstone,
mechanical engineer for GLHN A/E Inc. of Tucson, the project architects and engineers,
said the electrical and communication cables were run in duct banks - concrete-
encased banks housing individual conduits.
"They generally followed
the same route as the tunnel," he said. "We also had to construct a
new set of 15 kv high- voltage switch gears for the ducts."
On the
mechanical side of the contract, Sundt constructed a new 4,000- ton cooling tower
consisting of two 2,000- ton cells located in the Health Sciences Center central
plant.
The final phase of the infrastructure work involves an extensive
landscape and hardscape package to cover up the areas disturbed by construction
and tie together the new buildings that are under way or planned.
Sundt
has been able to maintain its schedule and has kept the project under budget,
Johnstone said.
"There's a lot of chance for disruption and other
problems on a job like this, but this one has gone seamlessly," he added.
|