| Plans for Pleasant Water
By K. Robert Wendel Better
tasting water is on tap for Phoenix residents.
|
Phoenix, along with other Valley cities, has long struggled with poor- tasting
tap water, but a new, 320-million-gallons-a-day water treatment plant on Lake
Pleasant Road will change that.
The new plant is being constructed in phases.
The first, an 80-mgd project, is under construction. The $228 million project
is scheduled for operation in February 2007, with construction finishing in mid-2006
followed by a startup period. Total contract value is $330 million
The
new treatment plant incorporates several systems that usually stand alone.
"Essentially,
this is the first time in the United States that all the different processes have
been put together in one system," said Troy Hayes, the plant-engineering
leader for the city of Phoenix. "All the systems work together to meet any
current or foreseeable regulations, so we are going above and beyond any standards
we have now and are even exceeding future regulations."
The project
employs a series of five processes to treat water: An active ballasted flocculation
system where sediment is separated; an ozone treatment system; a deep- bed filtration
through granular activated carbon; an ultraviolet treatment process; and chlorination.
Once the water is finished, it will be stored in a 40-million- gallon basin.
"Central
Arizona Project water is a difficult water to treat," said John Quarendon,
American Water project director. "With all these processes, you are going
to get a much better water aesthetic and you will really be able to taste the
difference."
Started in the 60s, the CAP is a system of canals that
bring water to cities around Arizona from the Colorado River. The water picks
up minerals and sediment on its journey from the snow packs of the Rocky Mountains,
making it difficult to treat.
The Lake Pleasant Water Treatment Plant is
the largest design-build-operate project in North America, with New Jersey-based
American Water Services as the prime contractor. The Phoenix offices of Black
and Veatch and McCarthy Building Cos. are providing design and construction services.
American Water Services has a 15-year contract to operate the project, with
a five-year option available. American Water Services is a division of London-based
Thames Water.
City of Phoenix officials went with the design-build-operate
contract for a variety of reasons. As the prime contractor and operator, American
Water Services is expected to deliver a higher- quality construction because it
will operate the plant for at least 15 years.
"We figured we could
get a better handle on costs and schedules by going with a builder/operator,"
Hayes said. "There are also cost savings associated, and we can get the project
delivered quicker by going with one design and building team."
The
project is requiring a massive amount of earthwork, with the Peoria office of
Ames Construction Inc. moving more than 400,000 cu. yds of dirt. The soils on
the 285-acre site were also a challenge, with much of the excavation done by blasting.
BCS Enterprises of Phoenix performed the demolition.
"It's been one
big dirt job," said McCarthy project manager Rich Distler. "We had a
mix of soils, with some river rock, but we blasted most of the structural sites
and we had a lot of hard rock trenching."
The plant actually sits
nearly 2 mi. away from its water source, the CAP canal, south of Lake Pleasant.
To
connect the plant with the water source, crews constructed an 11,500-ft.- long,
90-in. pipeline from the canal to the treatment plant's intake. Crews are in the
process of building a giant head works at the canal to intake the water.
The
canal's pump station is 45 ft. below grade.
Because of the site's size
and location, permitting was a major headache for the team. Part of the project
lies in Phoenix, with the intake in Peoria, so permitting from two cities was
needed, along with the Arizona Department of Environmental Quality, the U.S. Army
Corps of Engineers, The Arizona Historical Preservation Department, Maricopa County,
the CAP and APS.
And don't forget the BLM, Bureau of Reclamation and EPA.
Although the project uses an impressive 63,000 cu. yds of concrete, most of it
will be covered and below grade. There also are 18 different buildings such as
pump houses and equipment rooms. The project even has its own 67-kV substation
to electrify the plant.
Ludvik Electric Co. of Peoria is the electrical
contractor, with Able Steel of Mesa erecting and fabricating steel. Harris Rebar
of Phoenix is tying the rebar, while Coreslab Structures is providing the precast
concrete. Tempe's TriCity Mechanical is performing the plumbing, piping and mechanical
work.
There are also plans for a 7,600-sq.-ft. operations center.
"The
architecture is going to be significant, with poured-in-place concrete, core 10
steel and a lot of natural material," said architect Nader Kavakeb of Scottsdale's
Swaback Partners. "In the past, neighborhoods rejected these projects, so
municipalities have decided to make an art form for these building types."
In
addition to the poured concrete and steel, plans also call for gabion walls, tensile
structures and high-end masonry. The masonry block features two finishes, with
a rough-cut "mesa" stone on the exterior and a burnished and sealed
block on the interior.
Maverick Masonry, which is based in nearby Glendale,
will use more than 115,000 units on the project.
"It's one block with
two different finishes, so that is unique," said Gary Tieman, president of
Maverick Masonry. "Even though the units are more expensive, it will save
the city money because you won't have to do tile or gypsum board on the interior."
|