| Building it Big New
Civic Center to Energize Downtown
By
K. Robert Wendel The first phase of the $600 million Phoenix
Convention Center expansion should be completed by May.
Work on the downtown
project started in fall 2003 with site preparation, and plans call for 2.4 million
sq. ft. of new and remodeled convention space to be fully open by mid-2009.
|
The project consists of new west and north buildings and a renovation
of the south building. Work will wrap up on the renovation of the nearby Symphony
Hall this fall.
"We are hot and heavy in construction on phase one,
with 85 percent of the construction funds committed," said Nirmal Mangal,
vice president and managing principal in the Phoenix office of architect Leo A
Daly.
The west building is the first to open in 2006, followed by the
north hall in 2008, finishing off with the south convention remodeling in 2009.
Once the west building is finished, convention center activities will be shifted
to the new west hall and work will start on phase two.
Phoenix voters approved
$300 million in funding with the state of Arizona committing another $300 million.
The
new convention center is one of the largest construction projects in Arizona history
and it is also the largest "green build" effort in the United States.
The construction team is aiming for a basic Leadership in Engineering and Environmental
Design certification from the U.S Green Building Council.
Some "green"
techniques under discussion include installing solar panels on the roof and using
as much natural day lighting as possible.
"Everything about this
project is large," said Patrick Edwards, the lead designer and a principal
with the Phoenix office of Leo A Daly.
The new project more than triples
the size of the existing convention center, which is now the 67th largest convention
hall in the United States. When the project is completed, the new convention center
will be among the 20 largest convention centers in the nation.
City officials
said about 120,000 people use the existing hall each year, with projections showing
an estimated 345,000 convention delegates annually when construction is completed.
They added that each conventioneer spends an average of $1,500 during his or her
stay.
The city awarded a construction-manager-at-risk contract after reviewing
11 submissions on the design side and eight submissions on the construction side.
It settled on the tri-venture group of Hunt Construction of Phoenix, Alvarado
Construction of Denver and Russell Construction of Atlanta.
The city designated
that 10 percent of the $600 million project must go to minority or women-owned
businesses. HOK Venue set a higher goal to contract 20 percent, which is being
exceeded by 3 percent.
The project features a host of engineers, including
LSW Engineers Arizona Inc., Paul-Koehler Structural Engineers and David Evans
and Associates, all based in Phoenix, and Los Angeles-based Syska Hennesy.
Most
of the convention space sits 45 ft. below grade, with the new west hall eventually
connecting to the east hall under Third Street, creating 310,000 sq. ft. of contiguous
convention hall space. Monroe Street will become the haul road in and out of the
convention basement. The bays between columns are 90 ft. by 90 ft., with a 32-ft.-tall
ceiling.
Three other levels feature meeting rooms on the at-grade level,
conference rooms on the third level, and a ballroom on the fourth level.
Included
will be high-tech communication and multimedia system. A central utility corridor
will run underneath the below-grade convention hall.
The four above-grade
levels sit on massive steel beams with 808 ft. lbs. of load for every foot of
steel beam. The project calls for more than 25,000 tons of steel. "Steel
is a big issue because of the rapid acceleration of prices, so it's a cramp on
the project," Edwards said. "We had to go back and do some rigorous
value engineering to bring the costs back into line."
The city will
temporarily abandon Third Street while contractors open a cut to construct the
connection between the east and west halls. Third Street will come back up to
grade and become a two-way street. Washington Street also gets a makeover, and
its dip under the existing convention center will be eliminated.
Keeping
the massive convention center pedestrian friendly was a key objective for designers.
At the street level, plans call for retail shops and offices along the perimeter
of the building. At the main entrance, a soaring 70-ft.-tall glass curtain wall
opens into an air-conditioned atrium that is 90-ft. tall.
The street level
features sandstone accents and is themed with southwest architecture. The atrium
evokes a slot canyon while the sand stone echoes the stratified rock of the Grand
Canyon.
"We are trying to engage people at the street level, even
if they aren't going into the convention center," architect Mangal said.
"We also want the project to reflect the style and values that Arizona is
about."
Building
Barrow >>
|