| Ready in Reno
By K. Robert Wendel The first of five
planned speculative office buildings at the Northern Nevada Corporate Center in
south Reno is finished and occupied, and there are plans for permits to be pulled
for the second project.
|
Work on the first 45,000-sq.-ft. building started in October
2003, and tenants occupied the space 11 months later. Four more speculative offices
will be built at the 16-acre site.
The buildings will be laid out in a
sawtooth pattern, and architectural features will remain fairly consistent.
"We
had a learning curve, so the layout on the succeeding buildings is going to be
a little different," said Matt Clafton, vice president and general manager
of Panattoni Construction's Reno office. "We reduced the size of the lobby
and added another variable air volume box for redundancy."
Although
this $3.3 million project is a slab on grade, crews faced difficult environmental
issues. Pour drainage had created a soggy site, so before construction could start,
the parcel needed dewatering with pumps. Crews also constructed a dewatering trench
to keep the project dry in the future.
"The biggest issue before construction
was the dewatering," Clafton said. "We couldn't move until we took care
of that."
The two-story buildings are concrete tilt-up with some exposed
architectural steel elements. Builders went with tilt-up for ease and speed of
construction.
A curved exposed steel staircase punctuates of the office
lobby, which is finished with high-end materials such as granite. The exterior
is a combination of EFIS and dry-stacked stone, and there are 150 parking spaces
in the first phase.
"They wanted to blend the surrounding architecture
with a more efficient floor plan," said architect Jeff Turnipseed of Reno's
Johnson Blakely & Ghusn Architects.
"Panattoni wanted to compliment
the other projects but be more competitive from a leasing standpoint."
Because
the building backs to the I-395 freeway, architects wanted to create a presence
for it, so almost as much attention was paid to the back side as to the front.
The building is capped off with a single-ply roof, which is where the
mechanical systems are located. A parapet screens the roof and the gas-fired mechanical
systems.
"We have a five-year master plan and our intent is to start
a building every year," Clafton added.
|