| High Times By
Tony Illia A design-build approach fast tracked a $9.77 million expansion
of the High Desert State Prison near Las Vegas. It's only the second time the
state of Nevada has used the innovative procurement method that pairs the contractor
and architect together as a team.
|
The state Department of Corrections hired
KGA Architects of Las Vegas to develop bridging documents, which detail the project's
technical and programmatic requirements, to 85 percent completion.
Although
some design-build purists see bridging documents as a controversial and unnecessary
expense that amounts to designing the same project twice, backers of the approach
say it ensures a consistent level of quality and prevents a design-build team
from cutting corners. It also can help guarantee that the owner's objectives are
met, while expediting the permitting process.
The state issued request-for-qualifications
in mid-2003. It evaluated teams on experience, financial strength and background
before narrowing the list to three finalists. The winner was selected on a "best-value"
basis, where price accounted for 25 percent of the total score.
Team composition,
technical design, value and project controls were considered. Clark &
Sullivan Constructors' Las Vegas office was awarded the contract on Dec. 1, 2003,
with Phoenix-based Arrington Watkins Architects LLC as architect. Swisher &
Hall, AIA, Ltd. of Las Vegas was later hired as a consulting architect.
"We
moved and rotated the building, which saved $2 million in excavation, utility
and sitework costs," said Ron Vollmond, Clark & Sullivan's director of
project development.
"With rising labor and material prices, this
project might not have been built without the realized savings from a design-build
approach."
Located in Indian Springs, 46 mi. northwest of Las Vegas,
the prison site covers 21 acres and is 2 mi. around its perimeter. Repositioning
the building eliminated $250,000 worth of excavation and backfill needed to create
a level area as well as other associated infrastructure.
"We placed
the building using the site slope, which lowered the circulation area for the
loading docks and eliminated drainage systems, railings and retaining walls,"
said Lynn Arrington, principal of Arrington Watkins Architects. "We were
able to balance the site, taking advantage of the natural topography."
The
project called for a single-level, 60,000-sq.-ft. concrete tilt-up warehouse/distribution
facility to house the prison's industries program. The structure uses insulated
sandwich paneling, which saved an additional $40,000 in labor and materials.
Blakely,
Johnson & Ghusn Inc. of Reno, was the structural engineer for the warehouse
facility. Sitting on a slab-on-grade foundation, the facility is designed for
maximum flexibility to enable prison operators to subdivide space into multiple
bays.
The project also included a single-story, 14,620-sq.-ft. masonry-block
gymnasium with a full-length basketball court, craft areas, music rooms and lockers.
American Structural Engineers of Las Vegas, was the structural engineer
for the gym.
The building has closed-circuit television, alarm interfaces
and central monitoring controls. Both buildings are serviced by the prison's existing
central plant, which was designed to handle added expansion space.
Design-build
enabled the project to finish within 10 months, and it opened in September. The
same job under a traditional design-bid-method would have taken 20 to 24 months
to complete, said Jennifer Worchester, Clark & Sullivan's marketing coordinator.
The state Legislature recently funded another $45 million expansion for the five-year-old
High Desert Prison to add more inmate cells. The undertaking, still in the early
design stage, is scheduled to advertise for bids in early 2006.
|