| Bringing
Mass to the Arts Phoenix Art Museum Turns Up the Volume
By
Scott Blair When the Phoenix Art Museum expanded ten years ago,
the construction team took a loose campus of older buildings and unified them
with dramatic new structures. Since then the museum has grown both in attendance
and endowment, creating the need for another expansion.
|
"At any one time, the museum can only hang about
5 percent of its 17,000-piece collection," said Jim Ballinger, director of
Phoenix Art Museum. "We have long had a need to expand our gallery space
to show more of our collection and provide more space for moderately sized and
small touring exhibitions."
In 2001, Phoenix voters approved $18.2
million in bond funds for the >> museum's expansion. "Our challenge
was to to then raise another $23 million from private donors, corporations and
foundations in a less than perfect economic environment," Ballinger said.
The
expansion will add a new four-level gallery wing, a new 12,500-sq.-ft. lobby and
canopied exterior entry plaza, an outdoor sculpture garden and an expanded museum
store. Kitchell Contractors of Phoenix, Ariz. was chosen as the contractor for
the project.
One time-saving step to the renovation was to enlist the same
architect as the 1994 expansion, Todd Williams Billie Tsien Architects LLP of
New York City, N.Y. "We knew the premises and existing buildings well,"
said Felix Ade, project architect for the firm.
"The biggest challenge
was the conditions of the site had changed. Last time we had addressed the site
as a master plan, but there were several components of that plan that weren't
completed due to cost, such as a large 70-ft. fiberglass dome in the center of
the property." This left a central atrium where the museum's entryway was
without an anchor or focal point.
"Suddenly the property on the north
side of the museum campus became available and was purchased by the museum, so
the direction of the site development changed," Ade said. "We thought
during the renovation ten years ago that the museum's future expansions would
occur to the east. That's why we put the central mechanical plant and the loading
dock on the north side last time - it was the backside of the building then."
The
original entrance on the new renovation was to be on Central Avenue, as if people
would arrive on foot, on bike or on the bus, Ade added. But with the parking lot
on the north side of the lot being used by most of the visitors, those arriving
by car did not have a clear entryway into the museum.
The designers chose
to keep the plant and dock where they were to control the budget, but mask them
from view. "We are raising the parapet height and the central plant is being
renovated, with a new larger 250-ton chiller replacing the old one half that size,"
said John Rigsby, project manager for Kitchell Contractors.
The city street
which separated the existing museum with the newly purchased land was realigned,
forming a more logical intersection and allowing for an exterior plaza with the
new entranceway.
"The plaza will be comprised of granite pavers and
an 8-ft. tall water curtain fountain, which will provide both visual and sound
deadening from the busy streets nearby," Rigsby said. Steel beams cantilever
out over the plaza, creating a canopy for the outdoor plaza.
"One
of the stunning architectural features is the glass enclosure of the lobby where
glass sheet panels, 6-ft. wide and over 15-ft. high provide a grand arrival for
visitors," Ade said. "We wanted nothing to obstruct the view into the
lobby or out into the plaza."
The illusion of continuous space is
accentuated by the glass sheets, which are held in place with clear silicon joints
without frames or mullions. The sheets continue several inches beyond the ceiling
as if it was disappearing into it. >>
"The glass panels are
comprised of three, 1/2-in. layers sandwiched together, and weigh almost a ton
each," Rigsby said. B & B Glass, the Phoenix, Ariz.-based glazing contractor,
built a special attachment for the forklift with suction cups to transport the
sheets, Rigsby added.
Existing gallery space was converted into a tall,
canyon-like walkway which leads visitors into a new orientation space, located
where the old museum store was. The new store occupies a space twice the size
of the previous location.
For the new 40,000-sq.-ft. gallery addition,
crews shored up an 18-ft. deep excavation for the basement in a previously empty
part of the lot on the south side. "Half of the basement will be occupied
by mechanical systems, with the other half devoted to gallery space," Rigsby
said. Light wells with sandblasted glass and a reflecting pool were included for
additional impact.
Even though the campus has a central plant, the new
addition required additional mechanical systems. "The entire east wall is
filled with ductwork within a 7-ft. wide passageway," Rigsby said. "Air,
temperature and humidity control are all extremely important for a museum."
On
the floors above, the goal was to create as much open space as possible. "The
museum wanted big, open rooms to be able to build their own temporary walls to
the specifications of each exhibit," Ade said. "We had a very large
volume to add to the overall campus, but we didn't want it to stand out, so we
chose to connect them by using a similar material for the exterior pre-cast concrete
panels."
One of the most unique aspects of the 1994 renovation was
the green aggregate used in the pre-cast panels. In the current addition, a green
quartzite aggregate from Utah was chosen. "It uses a slightly different color
of aggregate - less obviously green and more gray," Ade said.
"The
aggregate had to be mined in the summer due to extreme winter weather restrictions,"
Rigsby said. "To get the proper matrix color, black Texas sand was used to
contrast with the aggregate."
The finish was sandblasted this time
for a more subtle look. "It doesn't attack the surface as much as water-washing,
which was used in the 1994 addition and brings out the aggregate texture more,"
Ade said.
The west side of the addition adjoins the 1994 addition. "One
of the challenges was tying the new structure into the old one, both mechanically
and structurally," Rigsby said. Kitchell had to raise the level of the floor
in the old addition to match the new floor height after the wall was cut out between
the two structures. "The gallery floor was filled with 8-in. thick high-density
foam and covered with a concrete slab. You might not think walking on foam would
be strong enough but it was chosen because you couldn't fill the gap with soil
due to the moisture, and compacting would add too much vibration, so we talked
with the architect and found this foam which supports 10-lbs.-per-sq.-inch."
The
museum is scheduled for completion mid-2006. In addition, 40,000 sq. ft. of outdoor
space at the heart of the campus will be transformed into a sculpture garden later
this year under a separate construction contract
Click here for next Renovation and Restoration Feature>
|