| A Concrete
Example Students Get New Model Architecture Building at UNM
By
Scott Blair As any professor knows, it's not easy inspiring students,
especially if the subject is architecture and it's being taught within a decades-old
furniture store or medical clinic building.
|
That is exactly what the University of New Mexico's
School of Architecture and Planning has had to endure since the program's inception
in the mid-70s.
But things are about to change as the school breaks ground
on the new $21.5 million School of Architecture and Planning and Fine Arts and
Design Library, also named the George Pearl Hall.
"The primary theme
of the design is: building as teaching tool," said Graham Hogan, senior associate
and project manager with Albuquerque-based Antoine Predock Architect, who did
the design of the building. "We wanted to reveal the building so the teachers
could use it and reference it, so all the building material, ductwork and conduit
is expressed in the large studio spaces."
Also working on the design
was executive architect Jon Anderson. Jaynes Corp. is the general contractor on
the 108,000-sq.-ft. cast-in place concrete and steel-framed building.
The
structure fits into a tight site near the university bookstore and major streets.
"We're right against the main access to campus, so we've looked really
hard at making sure everyone coming through the site is safe," said Brian
O'Connell, senior project manager with Jaynes.
The building will have four
stories above ground and one below, and will sit on a Geopier system foundation.
"The architectural concrete on the south wall is a big feature on
this building," said Darrel Massegee, senior superintendent with Jaynes Structures,
a division of the company that performs as concrete contractor on the project.
"This is a very difficult concrete job with cantilevers, shafts and block-outs."
The wall features a 40-ft. cantilever and massive 4-ft., 6-in.-thick walls.
However, they are not solid all the way through - a shaft penetrates the middle.
"The actual thickness is only 12-in. to the hollow area, and it is filled
with massive amounts of rebar," Massegee said. "You have to build it
piece by piece rather than building big mats and flying them in by crane."
"The
wall was a sacred piece for us, and we are thrilled it will be realized,"
Hogan said. "It was always on the chopping block due to cost. The wall acts
as a transition from campus to the city urban environment." >>
The
wall contains a large opening that features a recessed glass curtain wall. "The
building will look like an illuminated lantern behind this monumental wall, revealing
students working 24-hours a day behind this protective layer," Hogan said.
The
design originally included many green building techniques that were later value-engineered
out due to budget constraints, Hogan said. Some key green elements remain, such
as louvers that block direct sunlight but reflect light deep into the building's
interior.
"There are also controlled-dimming lighting which automatically
reads the natural light outside then dims various areas so it maintains a specific
level," O'Connell said.
The building will be assembled starting on
one end, with the elevator and seismic concrete core section built first all the
way to the fourth floor.
"After that, we are going to build the third
floor of the middle section first, and then fly the steel down through that to
build the second and first floors, because some of the beams and columns that
support the lower floors are actually attached to trusses that don't go all the
way down to the ground," Massegee said.
Crews will use 93-ft.-long,
type-one trusses for the third-floor steel. Four, 650-lb.-per-ft. steel beams
will also be utilized. The 34-ft.-long beams are not manufactured in the U.S.
and had to be shipped from Belgium.
Since the building is intended to
be scrutinized by future students, most of the structural elements will remain
exposed. "Ironworkers will love this building, because their work on other
projects always gets covered," Massegee said.
"Here, they can
bring their wives and say, 'Hey, we built that, right there!'"
Key
Players
Owner: UNM Dept. of Facility Planning General Contractor: Jaynes Corporation Architect: Antoine Predock Architect; Jon Anderson Architect Electrical: McDade-Woodcock, Inc Mechanical: Yearout Mechanical Concrete:
Jaynes Structures, Inc Steel: W & W Steel Co
Click here for next Albuquerque Activity Report Feature>>
|