| Phoenix Rising
New High Schools Sprout In Phoenix Desert
by Scott Blair
The Phoenix metropolitan area continuously faces population
growth year after year. While much of the region's infrastructure
and services struggle to keep pace with growth, public schools
are one of the most visible.
|
This year, several major high schools open to students, while
others are in planning or under construction. This roundup
will spotlight several of the most prominent projects.
The Coronado High School campus is undergoing a two-phase
construction project to replace most of the existing structures
as part of a successful 2004 school bond for the Scottsdale
Unified School District.
"That school really needed a facelift, and the facility
they are going to have is night and day to what they had before,"
said Bryan Dunn, preconstruction manager for the Phoenix office
of contractor Adolfson & Peterson.
The first phase began in June of last year and was turned
over to the school district in August upon completion. It
encompassed 165,346 sq. ft. of classroom and administration
space, along with a new central plant. Once school let out
for summer, phase two began with the demolition of existing
campus structures and the construction of 156,346 sq. ft.
of new classrooms and an auditorium.
"We were under very heavy time constraints because while
we were building this classroom building, we were demo-ing
about 80 percent of the campus," Dunn said. "From
a scheduling standpoint, to get that classroom completed,
it took having everyone on the same page from the beginning:
no matter what, the building had to be finished - there just
wasn't another option."
The new campus will include several key outdoor spaces, including
an outdoor dining area and a courtyard. The old layout included
many areas where the administration couldn't see students
which created security concerns. "It was a maze,"
said Brett Hobza, design architect on the project with the
Phoenix office of DLR Group. "Our design has a big open
courtyard where the principal's office overlooks, and they
can see virtually everything the students are doing. It's
a really big departure from the 1960's (when the original
campus was built)."
However, some existing elements will remain or be re-used.
A 20-ft. x 26-ft. ceramic tile mural featuring an abstract
musical motif was taken down and preserved from the old auditorium,
and will be reassembled on the exterior of the new one.
"Another key thing was to repeat the folded plate roof,
which was pretty much a trademark of the campus," Hobza
said. "They really appreciated our attempt to tie in
something that is an icon on that campus to the new construction."
The central plant is being replaced as part of the school
district's goal to reduce energy and maintenance costs, according
to Hobza. Other efficiency improvements include energy-efficient
glazing and improved site orientation.
Most of the new structures are masonry, though during the
preconstruction phase the large classroom building was switched
to structural steel. ""We were able to save about
two months out of the schedule which actually made it possible
to reach the end dates that we needed," Dunn said. "We
ran the cost model with standard CMU and we couldn't have
gotten the building done in time."
The team was able to keep the masonry look, however, by using
a masonry veneer over a steel-framed exterior wall system,
Hobza said.
Adolfson & Peterson and DLR Group are also constructing
the $57 million New Comprehensive High School in Laveen, Ariz.
The Phoenix Union School District project features nine buildings
on a 55-acre site just a few miles from the new Cesar Chavez
High School.
The 304,000-sq.-ft. campus is being designed around the district's
philosophy of a small learning community environment, where
the school's 2,500 students are split into four separate schools
of approximately 625 students, each with its own building
and identity. They are aligned along a winding, street-like
outdoor space. "Each building has a glass wall that looks
out to this circulation spine," said Thomas Patrick O'Neil,
principal in charge of the project with DLR Group. "You
can see the identity of each community's character from the
outside, but from the inside it is like eyes on the street."
One of the challenges was to bring all of the masonry buildings
out of the ground at the same time. "There's no one in
town that has enough manpower to cover nine buildings at one
time, so the sequencing becomes a challenge on how to phase
between the buildings to keep the crews working as efficiently
as possible and still make your schedule," said Brock
Huttenmeyer, preconstruction director with Adolfson &
Peterson. "We extensively qualified subcontractors at
bidding time to make sure they had the manpower required,
and we did extensive scheduling prior to bid."
DLR Group incorporated student and administration feedback
in several key aspects of the project, including the library.
"Students don't go to a library to pull a book off the
shelf like they did in year's past," O'Neil said. "So
to encourage the use of the library, we provided the backdrop
of a café. We wanted the library to become not only
symbolic, but a very important part of the campus."
The school will also feature a central plant with a four-pipe
mechanical system in accordance with the school district's
quality standards.
Another of the district's schools, Camelback High School,
will also feature a new four-pipe system central plant as
part of its $27 million, 175,000-sq.-ft. classroom replacement
and addition.
Camelback High School was split into three phases. The first
was a kitchen remodel completed last summer. Phase two began
August 2005 with the demolition of a parking lot and the construction
of the three-story, 102,000-sq.-ft. East Academic Building.
As that phase finished up in August, the year-long third phase
began with demolition of several old buildings and the construction
of a new 68,000-sq.-ft. classroom and library building on
the northeast corner of the campus.
"School has been in session during the project,"
said project engineer Jason Wiley with Phoenix-based contractor
D.L. Withers Construction. "We worked with the school
and did a weekly broadcast with them to give students an update
on construction as a necessity for safety."
Camelback's design also uses the small school concept with
2,400 students split into groups of roughly 700.
Each small school has its own separate color scheme as well
as separate courtyards, commons areas and administrative offices.
"We are trying to make it so the students will like being
there, with the color schemes and some areas that they will
enjoy rather than just walking into a building with corridors,"
said Michael Rhodes, project manager with Architectural Resource
Team, the Phoenix-based architect on the project. It is designed
to give the students a sense of space and identity, which
will hopefully cut down on vandalism and graffiti, Rhodes
added.
Natural lighting is used throughout the new buildings. The
height of each commons area extends up the full three stories,
with a skylight above and ample glazing looking out onto the
courtyards.
"There have been three school principals since we started,
and each one has their own idea of what they want in the new
building," Wiley said. "I've really enjoyed working
with the administration and watching what they want and being
able to be a part of delivering it."
Key Players
Camelback High School
Architect: Architectural Resource Team
GC: DL Withers Construction
Coronado High School
Architect: DLR Group
GC: Adolfson & Peterson
New Comprehensive
Architect: DLR Group
GC: Adolfson & Peterson
Click
here for Next Feature Story >>
|