|
Engineering the Future
UNM Embarks on a New School of Engineering
By Scott Blair
The $42 million Centennial Engineering Center at the University of New Mexico in Albuquerque will replace several outdated existing buildings for the School of Engineering. The 147,445-sq-ft building will be the largest new structure ever built at the main campus.
|
After idling on the drawing board for nearly 10 years, the
Centennial Engineering Center finally broke ground in October
at the main Albuquerque campus of the University of New Mexico.
The new center was needed to consolidate all engineering disciplines
at the college which were scattered throughout the campus
in aging buildings up to 60 years old.
Originally the building was slated to be done in two separate
parts. "We thought it would be a $30 million project
built in phases because it would be impossible to ask for
that much in one piece," says Joe Cecchi, dean of the
School of Engineering at UNM. The school began to be successful
in raising funds through the state legislature and other sources.
That's when construction costs for materials and labor began
escalating.
"It looked like with the rate of escalation, we were
barely keeping up with it and we were marking time. UNM recognized
this and decided we would bond for some part of the money
for a capital project using student fees."
Right before the final appropriation at the legislature, hurricane
Katrina hit, causing yet another materials price escalation.
Despite these challenges, Cecchi says: "The good part
is we are now building the entire building, rather than constraining
programs to fit into one half of the building. The end result
is a fully-funded, $42 million project that is the largest
ground-up building ever on the main campus."
The school retained Albuquerque design firm Van H. Gilbert
Architect, which partnered with Boston-based architect Shepley
Bulfinch Richardson & Abbot, to design the 147,445-sq-ft
structure. Albuquerque-based Bradbury Stamm Construction was
selected as the general contractor.
The quadrangle-shaped building will provide students and faculty
with modern classroom and research laboratories in four wings
surrounding a central courtyard.
"Engineering is a contact sport," Cecchi says. "We've
got to have the latest facility to teach engineering and computer
science."
The design intent balances the 21st century biomedical and
engineering concepts happening inside with the existing flavor
of UNM. "We're trying to give a high-tech look to it,
but is it very much a traditional UNM Building," says
Michael Hill, project manager with Van H. Gilbert Architect.
"To the greatest extent it picks up the UNM fabric of
stucco and sloped, battered walls, but then there's glass
and metal solar shades."
In October, the aging engineering buildings occupying the
site were demolished, leaving just enough space in this high-density
part of the campus for the new building.
"This is really an urban-type construction project with
almost no access," Hill says. "Everything is staged
offsite and will be brought to the site, lifted off the truck,
put up into a place or a staging area in the building somewhere.
Even the workers have to be bussed in."
The shoring and excavation was recently completed, removing
37,000 cu yds of material to roughly 18 ft below-grade. "Our
shoring goes right up to where the site ends," says Dan
Lyons, project manager with Bradbury Stamm.
The foundation system is auger-cast concrete piles with pile
caps and concrete grade beams. The four-story, structural
steel building features one story which sits below grade.
"When we erect the structural steel, we are going to
have to do it from down inside the basement," Lyons says.
"Usually you'd set up a crane and move around the building,
but due to site restrictions, we're going to have the crane
down inside the basement and work our way out."
The exterior will feature an EIFS system with the stucco finishing
over the face, but one of the most striking elements will
be the number of windows in the structure.
"Roughly half the windows face the internal courtyard,"
Cecchi says. "We didn't ask for that, but it was in Van
Gilbert's concept from the start, and we obviously bought
into it because we could see what a tremendous feature that
is going to be."
The labs will be on the north and south wings of the buildings.
While they share the building's mechanical systems, they will
also have an added once-through exhaust system attached to
fume hoods.
The school has taken advantage of some unique benefits as
a result of the project. "The contractors are very open
to having our civil engineering and construction classes visit
onsite," Cecchi says. "We are starting a lecture
series to educate the rest of the school of engineering on
how a building like this is built - it is a great educational
opportunity."
Key Players
Owner: University of New Mexico
Architect: Van H. Gilbert
Architect
General Contractor: Bradbury
Stamm
Electrical: Chaparral
Electrical Contractors
Mechanical: Miller Bonded
Concrete: Noel Company;
Materials Inc.
Steel: Structural Services;
W & W Steel
Click here for Next Feature Story >>
|