|
Full Circle
Red Mountain Freeway Completes East Valley Loop
By Scott Blair
The final section of the Red Mountain Freeway in Phoenix's
east valley will complete a route two decades in the making.
Featuring miles of roadway, numerous bridges and complicated
flood management facilities, finishing this project won't
be easy.
An epic saga two decades in the making, Red Mountain Freeway's
road to completion started in 1985 with the passage of a half-cent
sales tax by Maricopa County voters. 22 years later, motorists
will be able to drive in a complete loop around the cities
of Tempe, Mesa, Chandler and Gilbert upon completion of the
final two sections between Power Road and Southern Ave. in
late 2008.
The 4.83-mi section between Power Road and University Drive
is the largest of the two projects. Phoenix-based contractor
Pulice Construction Inc. was awarded the project and began
construction in February 2006. Coming in at a cost of $195
million, it is one of the largest single projects the Arizona
Department of Transportation has ever done.
It is also one of the fastest timelines for such a complex
project, with a completion date of September 2008.
"We were looking at a relatively short timeline for design
delivery and the construction phase while coordinating with
many outside agencies to get this project done," says
Mike Bruder, project manager with ADOT.
The second project, located immediately to the south, is valued
at $67.4 million and will construct 2.1 mi. of six-lane urban
freeway from University Drive to Southern Avenue. Parsons
Brinckerhoff designed this section, with Pulice again as the
general contractor.
These are the final two projects funded by Proposition 300,
a sales tax that was implemented 22 years ago to fund regional
transportation projects.
Both projects cross land controlled by a variety of city,
county and state governmental agencies. The larger project
passes through a Maricopa County Flood Control area, requiring
the partial relocation of a dam and its impoundment.
"It was very complex from drainage, geotechnical, the
dam and the sheer magnitude of just the roadway improvements
themselves," says Michael Chase, P.E., vice president
and principal transportation engineer with the Phoenix office
of Stanley Consultants, the lead design firm on the Power-University
section.
This section required the movement of over 5 million cu yds
of material, partly due to the relocation of the impoundment.
"We've created the same amount of impoundment but in
a smaller area because the freeway footprint took up what
used to be floodplains" says Steve Campbell, project
manager with Pulice.
The project was able to utilize 3 million cu yds of the material
in other areas of the project, with 2 million hauled off as
waste. "At times on our off-site haul, we were running
up to 120 trucks a day," Campbell says.
The area will be contour-graded in consideration of a future
park for the city of Mesa, according to Chase.
Crews are also modifying the 18,000-ft-long length of the
dam by installing a filtering device meant to strengthen the
dam and reduce fissuring, a common problem afflicting flood
control dams in the Valley.
"We are basically creating a 30-in.-wide slot in the
center of the dam and putting in an aggregate central filter
material down the middle," says Mark Soyster, vice president
of operations with Pulice. In most cases the slot ranges in
depth between 25- and 30-ft, but in some spots it exceeds
40-ft deep. "It's very unique and has been a challenge,
but we are moving forward." since much of this leg is
depressed below grade. Some dirt was reused in a way that
pleased nearby residents, according to Frank Medina, Arizona
manager for Parsons Brinckerhoff.
"In one area we were able to eliminate the sound wall
and replace it with an earthen berm," he says. "It
is not as hard of a feature, but is still the same height
as the adjoining walls."
The south project has 13 reinforced concrete box culverts,
while the Power-University project has 16. The smallest is
8-ft tall by 8-ft wide and 200-ft long, but they range all
the way up to 24-ft by 16-ft and 400-ft-long, Campbell says.
Many are used for equipment access to the Central Arizona
Project canal that runs the length of the project.
Of
the seven major crossroads that were part of the two projects,
the Power Road bridges are the longest and most unique. The
943-ft-long, 8-span bridges are comprised of pre-cast, pre-stressed
concrete girders and also span the CAP canal. Each bridge
will carry three lanes of traffic in each direction, but are
built 87-ft 8-in. wide to allow for future expansions to four
general purpose lanes plus an HOV lane, Chase says.
The bridge design required the use of straddle bent piers.
"Because of the large skew of the roadway and the long
span, they had to go with this unique system," Soyster
says. The four straddle bents are comprised of a series of
pre-cast girder plys bolted together to literally straddle
the CAP canal. "Then we built the pier columns on top
of the straddle bents and then built the pier caps on top
of those."
Another unique facet of the project is the use of roundabouts
on the McKellips Road and Brown Road interchanges.
"The roundabouts were an integral part of the community
involvement, and it was a neighborhood decision. They were
chosen because modern roundabouts have been proven to increase
safety over traffic signals," says Diane D'Angelo, public
spokesperson for ADOT.
Key Players
Owner:
Arizona Dept. of Transportation
Design:
Stanley Consultants; Parsons Brinckerhoff
General Contractor:
Pulice Construction
Subcontractors:
McNeil Brothers; Endo Steel; CS Construction; Carlson Masonry
Click here for next Feature Story >>
|