| Are "Pay-if-Paid" Clauses
Valid in Nevada? By
Leon F. Mead II, Esq.
Six years ago, the State of Nevada was rocked
by the opening of the Venetian Casino Resort. Not the opening night party but
the legal battle over the interpretation of "common" construction clauses
and their impacts on the Nevada construction business.
|
The glare of the spotlight on the minimal legal guidance from
Nevada courts available at that point brought many "issues of first impression"
to the Nevada trial court handling the $450 million mechanics lien and construction
claim case (In re: Venetian Casino Resort) as well as to the Nevada Supreme Court,
and new and untested laws were passed by the Nevada Legislature. The reverberations
can still be seen in many areas, including the current debate over the viability
of a "pay if paid" clause.
A "pay-if-paid" clause
is short-hand for a subcontract provision that shifts the burden of payment for
a subcontractor's work from the general contractor to the owner, if the owner
never pays the general contractor for the subcontractor's work. By making payment
from the owner an "express condition precedent" to payment becoming
due to the subcontractor, the general contractor seeks to insulate himself from
the risk of the owner's non-payment. By contractually agreeing that payment is
not due until the owner pays, the subcontractor bears the entire risk of owner
default. Many American courts have held such clauses to be unenforceable; interpreting
them instead to be "pay-when-paid" clauses which merely provide the
general contractor a reasonable period of time (6 months or so) to collect the
payment from the owner before the subcontractor is able to collect from the general
contractor directly. Nevada's Supreme Court has never dealt with the viability
of such clauses. One of the legislative knee-jerk reactions to the Venetian
case was the enactment of the Nevada Private Work Prompt Payment Act or "NPWPPA"
(NRS 624.606, et seq.), which trumped many tools used by owners and higher-tier
contractors to justify withholding payments to lower-tier contractors. In essence,
the NPWPPA requires payment be made to lower-tier contractors within very short
time limitations, except under significantly limited circumstances and then only
after written notice is provided. If the withholding is disputed or not justified,
a lower-tier contractor is legally authorized to stop working on the project until
payment is made.
One of the legitimate reasons to not pay under the law
is the existence of a "valid" clause making payment contingent upon
receipt of payment from the owner; however, even in such circumstance the subcontractor
is legislatively allowed to stop work. Nowhere in the NPWPPA is a pay-if-paid
or pay-when-paid clause expressly authorized or validated. Moreover, as the NPWPPA
provisions expressly invalidate contract clauses that waive or modify the provisions
of the NPWPPA, a persuasive argument can be asserted that the clauses are invalid
entirely. Based on the NPWPPA, some administrative representatives, such as investigators
with the Nevada State Contractors' Board, have asserted that pay-if-paid provisions
are invalid under the law. The Nevada Supreme Court has yet to take up the issue
and most general contractors will not want to fund the litigation to obtain such
a decision.
General Contractors therefore should be wary of relying solely
on a "pay-if-paid" provision to justify failing to pay a subcontractor.
While the NPWPPA does reference pay-if-paid clauses in several places, the overall
effect of the legislation may be contrary to their enforceability. General contractors
need to document legitimate problems with a subcontractor's work to justify a
lack of payment, even when an owner is failing to pay. If withholding is not legally
or factually justified, the wise general contractor becomes an advocate for his
subcontractor. If the owner is not justifiably withholding a subcontractor's payment,
the general must take steps under the NPWPPA to stop work on his own until the
owner resolves the issue or run the risk of contractual liability to the subcontractor.
While this may not entirely shield a general contractor from liability to the
sub, it may engender a relationship that will make the subcontractor easier to
deal with if the lack of payment results in a legal dispute.
Eventually,
the effect of the NPWPPA on a pay-if-paid provision will be dealt with by a Nevada
court. Until that time, a contractor cannot begin work in the State of Nevada
and assume the laws that apply in other states apply here too. As a result of
the Venetian (and other high profile construction cases), Nevada has its own set
of rules that are simply unique. Being aware of the uniqueness may make the difference
between success and failure for your business.
Leon
F. Mead II, Esq. is the founding and managing partner of Mead Pezzillo LLP. Mead
has established one of the most successful and respected law practices in Nevada.
Mead Pezzillo specializes in construction law and can be reached at (702)
233-4225 or www.meadpezzillo.com.
|